01

Complete project overview

MahaRERA · Registration filing
Buildings
2
Land area
1,165 sq m

Timeline

RERA registeredNov 2025
Proposed completionDec 2029
TodaySep 2026
Construction progress
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Aditya Samruddhi Enterprises

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400024
Survey no.
CTS No. 6(pt)
North boundary
17.5M Wide Existing Road
East boundary
12.2M Wide Existing Road
South boundary
Building No 151
West boundary
Building No 98
What’s nearby
Schools1 school within 1km
HealthcareHospital 115m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.2km away · Gym or sports centre 1.8km away · 4 restaurants and cafes within 1km
ShoppingSupermarket 249m away · Bank 175m away
Getting around
Expressway 678 m · Santa Cruz – Chembur Link RoadPrimary road 856 m · Lal Bahadur Shastri MargRailway line 262 mRailway station 361m away (Kurla)6 bus stops within 500m
Water & environment
Water body 173 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. CTS No. 6(pt)
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,201 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,548 projects the radar draws within 6 km — every kind, every stage — 819 are residential projects still under way. This list keeps only those, and looks further out.

42 projects within 1 km — showing the nearest 6.

40 m awayResidential / Group Housing

OM NANDADEEP CO-OP. HSG. SOC. LTD.

OM NANDADEEP CO-OP HOUSING SOCIETY LIMITED · Kurla

Jan 2024registered
Oct 2026target completion
Scale65 flatsAuthorityMahaRERA
40 m awayResidential / Group Housing

SAYBA ELEGANT

STAR AURA · Kurla

Jul 2023registered
Mar 2026target completion
Scale115 flatsAuthorityMahaRERA
40 m awayMixed

SAYBA CRYSTAL

AMOOL ENTERPRISES · Kurla

Jul 2024registered
May 2027target completion
Scale185 flatsAuthorityMahaRERA
40 m awayResidential / Group Housing

SAYBA ROYAL

M/S. STAR RISE · Kurla

Jan 2025registered
Dec 2026target completion
Scale152 flatsAuthorityMahaRERA
40 m awayMixed

Sayba Iris

STAR RISE · Kurla

Jan 2026registered
Jan 2029target completion
1 open complaintScale151 flatsAuthorityMahaRERA
140 m awayResidential / Group Housing

ELIXIR ONE

ELIXIR PROPERTIES LLP · Mulund W · CTSO Mulund

Feb 2026registered
Dec 2028target completion
Government Guidance Rate₹1,22,033/sq ydScale24 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.