TNRERA/29/BLG/0228/2026 · TNRERA · https://gethorizon.in/projects/ankur-azalea-m28peg3o

01

Complete project overview

TNRERA · Registration filing
Description
Registration for Stilt Floor + 4 Floors + 5th Floor part Residential Building (Height- 18.30m with Gym & Association room in 5th Floor) with 18 Dwelling Units at Regularised Plot No. 17, Chanakya Main road, Annamalai Avenue, Nolambur, Chennai. Comprised in S.Nos. 109/1 & 109/2 (Document), S.Nos.109/1A2 & 109/7 (Patta) of Nolambur Village , Maduravoyal Taluk , Chennai District.
Registration no.
TNRERA/29/BLG/0228/2026

Timeline

RERA registeredJul 2026
Proposed completionMar 2029
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

Ankur Realty Developers LLP (Developer)

Ankur Realty Developers LLP (Developer)Promoter
1Projects
1Cities
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

TNRERA · Registration filing
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.0km away · 2 clinics within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.6km away
ShoppingNo supermarket within 2km · Bank 879m away
Getting around
Expressway 1.7 kmPrimary road 840 m · Chennai - Chittoor - Bangalore Road (Old NH4)No metro or railway within 5kmBus stop within 1km
Water & environment
Water body 662 m
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

CMDA (Chennai Metropolitan Development Authority)

CMDA (Chennai Metropolitan Development Authority)
Planning Permissionapproved 3 Jul 2026 · 2 mo ago
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

CMDA (Chennai Metropolitan Development Authority)

Metropolitan development authority

Has approved 1,914 RERA projectsabout 1 in 2 in Tamil Nadu, more than any other body in the state.

Builders
1,310
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

456 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 49 projects the radar draws within 6 km — every kind, every stage — 41 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

10 m away

Megh Aarika

MEGH PROMOTERS PRIVATE LIMITED

Mar 2024registered
Dec 2028target completion
AuthorityTNRERA
960 m away

KG Impressions

K.G.Foundation (P) Ltd.

Nov 2021registered
Jul 2026target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.