Complete project overview

K-RERA · Registration filing
Units
150 units
Mix
78 × 2BHK · 72 × 3BHK
Booked
132 of 150 filed sold/bookedas declared in the RERA filing
Buildings
2
Land area
6,721 sq m
Floor area
24,062 sq m
Description
ARTECH METROPOLIS

Timeline

Project startedOct 2017
RERA registeredApr 2021
Proposed completionDec 2023
TodayJul 2026
Construction progress

69% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps etc15%
Completion of terraces floor each building20%
Electrical Fittings25%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc35%
Sanitary Fittings40%
Fire Fighting Fittings and Equipment45%
The external plumbing and external plastering60%
Staircases, Lifts Wells75%
Overhead and Underground Water Tanks.75%
Basement(s) and Plinth85%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings95%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Slabs of Super Structure100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

18 of 150 available
TypeArea sq mAvailable
3BHK1064 of 36
2BHK7610 of 58
2BHK822 of 20
3BHK1022 of 36

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

ARTECH REALTORS PRIVATE LIMITED

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
17Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,804 homeson the public record across 17 projects
3,57,028 sq mbuilt-up filed
72,636 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporationthis project11 of 17 projects
Kollam Municipal CorporationMunicipal Corporation2 of 17 projects
Karakulam Grama PanchayatGrama Panchayat1 of 17 projects
Thiruvalla MunicipalityMunicipality1 of 17 projects
ThiruvananthapuramLocal body (LSGI)1 of 17 projects
Trissur Municipal CorporationMunicipal Corporation1 of 17 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
MUKKOLA
Village
ULOOR
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695015
Survey no.
103/4
Patta no.
1170
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.7km away · Library 867m away
HealthcareHospital 1.6km away · 2 clinics within 1km
LifestylePark 1.4km away · Gym or sports centre 837m away
ShoppingSupermarket 825m away · Mall 1.1km away · Bank 916m away
Getting around
Primary road 742 m · Thiruvanathapuram - Thenmala RoadNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 336 m · Karimpuvila PondRiver 549 m · Killi River
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thiruvananthapuram Municipal Corporation

Municipal Corporation
approved 18 Jun 2018 · 8 yrs ago
Building Permit no. UE1/BA-342/15Survey no. 103/4

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan UE1/BA-342/15 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thiruvananthapuram Municipal Corporation

Municipal corporation / municipality

Has approved 224 RERA projectsabout 1 in 7 in Kerala, more than any other body in the state.

an apartments market91% apartments · 9% plotted layouts. Apartments like yours are this body's core business.

Builders
90
On record
12,045 flats · 635 plots
Since
2021

More apartment-heavy than Kerala overall — 91% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.