HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
60 units
Mix
36 × 3BHK · 24 × 2BHK
Booked
50 of 60 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,136 sq m
Floor area
11,401 sq m
Description
ARTECH PALM MEADOWS

Timeline

Project startedOct 2018
RERA registeredJun 2021
Proposed completionDec 2023
TodayJul 2026
Construction progress

64% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings30%
Fire Fighting Fittings and Equipment45%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Electrical Fittings60%
The external plumbing and external plastering60%
Installation of lifts, water pumps etc65%
Overhead and Underground Water Tanks.70%
Completion of terraces floor each building80%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Staircases, Lifts Wells100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 60 available
TypeArea sq mAvailable
3BHK1361 of 6
3BHK1124 of 24
3BHK1032 of 6
2BHK813 of 24

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

ARTECH REALTORS PRIVATE LIMITED

CompanyPromoter type
Kollam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
17Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,804 homeson the public record across 17 projects
3,57,028 sq mbuilt-up filed
72,636 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation11 of 17 projects
Kollam Municipal CorporationMunicipal Corporationthis project2 of 17 projects
Karakulam Grama PanchayatGrama Panchayat1 of 17 projects
Thiruvalla MunicipalityMunicipality1 of 17 projects
ThiruvananthapuramLocal body (LSGI)1 of 17 projects
Trissur Municipal CorporationMunicipal Corporation1 of 17 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
POLAYATHODE
Village
MUNDAKKAL
Taluk
Kollam
District
Kollam
Pincode
691010
Survey no.
15/1-2,15/4,15/4-2
Patta no.
13754,13753
What’s nearby
Schools1 school within 500m · 9 educational institutions within 1km · College or university 728m away
HealthcareHospital 296m away · 1 clinic within 1km · Pharmacy within 500m
LifestylePark 1.6km away · Gym or sports centre 1.2km away · 8 restaurants and cafes within 1km
ShoppingSupermarket 214m away · Mall 26m away · Convenience store within 1km
Getting around
Expressway 2.9 km · Salem - Kochi - Kanyakumari RoadPrimary road 90 m · Salem - Kochi - Kanyakumari RoadRailway line 245 m · Kollam -Thiruvanathapuram LineRailway station 1.5km away (Kollam Junction)4 bus stops within 500m
Water & environment
Water body 142 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kollam Municipal Corporation

Municipal Corporation
approved 13 Dec 2017 · 8 yrs ago
Building Permit no. PW.5/BA/16/16-17Survey no. 15/1-2,15/4,15/4-2

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan PW.5/BA/16/16-17 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kollam Municipal Corporation

Municipal corporation / municipality

Has approved 11 RERA projects0.7% of Kerala.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
9
On record
579 flats · 0 plots
Since
2021

More apartment-heavy than Kerala overall — 100% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.