HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
59 units
Mix
59 × 1RK
Booked
45 of 59 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,040 sq m
Floor area
2,539 sq m
Description
CASADEL QUEENSTOWN

Timeline

Project startedSep 2022
RERA registeredNov 2022
Proposed completionNov 2027
TodayJul 2026
Construction progress

85% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Electrical Fittings90%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc90%
Staircases, Lifts Wells95%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

14 of 59 available
TypeArea sq mAvailable
1RK263 of 9
1RK201 of 7
1RK151 of 4
1RK230 of 3
1RK190 of 1
1RK281 of 1
1RK180 of 4
1RK461 of 1
1RK251 of 2
1RK202 of 19
1RK180 of 4
1RK384 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

CASADEL BUILDERS INDIA PRIVATE LIMITED

CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
12Projects
1Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
401 homes · 99 plotson the public record across 12 projects
28,917 sq mbuilt-up filed
26,356 sq mplotted area
34,879 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kunnathunadu Grama PanchayatGrama Panchayat3 of 11 projects
Kochi Municipal CorporationMunicipal Corporation2 of 11 projects
Choornikkara Grama PanchayatGrama Panchayat1 of 11 projects
Edathala Grama PanchayatGrama Panchayat1 of 11 projects
Kalamassery MunicipalityMunicipality1 of 11 projects
Thrikkakara MuncipalityLocal body (LSGI)this project1 of 11 projects
Thrikkakara MunicipalityMunicipality1 of 11 projects
Varapuzha Grama PanchayatGrama Panchayat1 of 11 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
VALAVAKKATTU ROAD
Village
KAKKANAD
Taluk
Kanayannur
District
Ernakulam
Pincode
682030
Survey no.
117/10
Patta no.
4721
What’s nearby
SchoolsNearest school 1.9km away · Library 1.4km away
HealthcareHospital 1.6km away · Clinic within 2km · Pharmacy within 500m
LifestylePark 2.0km away · Gym or sports centre 1.4km away · 32+ restaurants and cafes within 1km
ShoppingSupermarket 297m away · Convenience store within 1km · Bank 467m away
Getting around
Primary road 901 m · Ernakulam - Thekkady RoadRailway line 4.3 kmMetro station 994m away (InfoPark I Station)9 bus stops within 500m
Water & environment
Canal 263 mWater body 758 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thrikkakara Muncipality

Local body (LSGI)
approved 25 Jan 2022 · 4 yrs ago
Building Permit no. TP1-BA-290/2020Survey no. 117/10
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan TP1-BA-290/2020 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.