HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
14 units
Mix
14 × 3BHK
Booked
12 of 14 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
465 sq m
Floor area
1,272 sq m
Description
SKYSCAPE

Timeline

Project startedApr 2018
RERA registeredFeb 2022
Proposed completionApr 2022
TodayJul 2026
Construction progress

87% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

2 of 14 available
TypeArea sq mAvailable
3BHK8002 of 14

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

CASADEL BUILDERS INDIA PRIVATE LIMITED

CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
12Projects
1Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
401 homes · 99 plotson the public record across 12 projects
28,917 sq mbuilt-up filed
26,356 sq mplotted area
34,879 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kunnathunadu Grama PanchayatGrama Panchayatthis project3 of 11 projects
Kochi Municipal CorporationMunicipal Corporation2 of 11 projects
Choornikkara Grama PanchayatGrama Panchayat1 of 11 projects
Edathala Grama PanchayatGrama Panchayat1 of 11 projects
Kalamassery MunicipalityMunicipality1 of 11 projects
Thrikkakara MuncipalityLocal body (LSGI)1 of 11 projects
Thrikkakara MunicipalityMunicipality1 of 11 projects
Varapuzha Grama PanchayatGrama Panchayat1 of 11 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
PINARMUNDA
Village
KUNNATHUNAD
Taluk
Kunnathunad
District
Ernakulam
Pincode
683565
Survey no.
346/13-19 346/13-4
Patta no.
9216 9438
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 852m away
LifestyleNo parks within 2km
ShoppingSupermarket 1.3km away · Convenience store within 500m
Getting around
Expressway 4.2 km · Kochi - Madurai - Dhanushkodi RoadPrimary road 3.1 km · Ernakulam - Thekkady RoadRailway line 3.1 kmMetro station 3.3km away (InfoPark I Station)2 bus stops within 500m
Water & environment
Water body 491 mCanal 1.6 km
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kunnathunadu Grama Panchayat

Grama Panchayat
approved 22 Nov 2017 · 8 yrs ago
Building Permit no. A2-6780/16Survey no. 346/13-19 346/13-4

The promised possession date (1 Apr 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A2-6780/16 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kunnathunadu Grama Panchayat

Grama panchayat

Has approved 9 RERA projects0.6% of Kerala.

a plotted-layout market22% apartments · 78% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
4
On record
77 flats · 183 plots
Since
2021

More layout-heavy than Kerala overall — 78% plots here vs 19% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.