Complete project overview

K-RERA · Registration filing
Units
49 units
Mix
36 × 1RK · 9 × 1BHK · 3 × 2BHK · 1 × Shops and Showrooms
Booked
17 of 49 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,218 sq m
Floor area
2,861 sq m
Description
CASADEL TOWNCASTLE

Timeline

RERA registeredAug 2023
Project startedSep 2023
Proposed completionDec 2027
TodayJul 2026
Construction progress

47% overall, as filed

Sanitary Fittings0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Staircases, Lifts Wells60%
Overhead and Underground Water Tanks.70%
The external plumbing and external plastering80%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Completion of terraces floor each building100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

32 of 49 available
TypeArea sq mAvailable
1RK213 of 3
1RK161 of 6
1BHK272 of 3
1BHK223 of 3
1RK2210 of 12
1RK232 of 3
1BHK272 of 3
1RK221 of 3
Shops and Showrooms3651 of 1
1RK141 of 3
1RK242 of 3
1RK151 of 3
2BHK443 of 3

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

CASADEL BUILDERS INDIA PRIVATE LIMITED

CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
12Projects
1Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
401 homes · 99 plotson the public record across 12 projects
28,917 sq mbuilt-up filed
26,356 sq mplotted area
34,879 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kunnathunadu Grama PanchayatGrama Panchayat3 of 11 projects
Kochi Municipal CorporationMunicipal Corporation2 of 11 projects
Choornikkara Grama PanchayatGrama Panchayat1 of 11 projects
Edathala Grama PanchayatGrama Panchayat1 of 11 projects
Kalamassery MunicipalityMunicipalitythis project1 of 11 projects
Thrikkakara MuncipalityLocal body (LSGI)1 of 11 projects
Thrikkakara MunicipalityMunicipality1 of 11 projects
Varapuzha Grama PanchayatGrama Panchayat1 of 11 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Kalamassery
Village
THRIKKAKARA NORTH
Taluk
Kanayannur
District
Ernakulam
Pincode
682033
Survey no.
493/7,493/5
Patta no.
25348
What’s nearby
Schools1 school within 1km · 3 educational institutions within 1km · College or university 778m away
HealthcareHospital 202m away · 3 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Playground within 500m · Gym or sports centre 246m away
ShoppingSupermarket 232m away · Mall 1.6km away · Bank 40m away
Getting around
Expressway 51 mPrimary road 197 m · HMT Ring RoadRailway line 264 mMetro station 183m away (Cochin University)6 bus stops within 500m
Water & environment
Canal 715 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kalamassery Municipality

Municipality
approved 4 Apr 2023 · 3 yrs ago
Building Permit no. BA-68/2022Survey no. 493/7,493/5
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BA-68/2022 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kalamassery Municipality

Municipal corporation / municipality

Has approved 11 RERA projects0.7% of Kerala.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
11
On record
509 flats · 0 plots
Since
2021

More apartment-heavy than Kerala overall — 100% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.