HORIZONMarkets
01

Complete project overview

RERA Karnataka · Registration filing
Status
Completed
Towers
50
Land area
7,29,395 sq m
FAR sanctioned
0.7
Covered area
4,04,046 sq m
Open area
3,25,348 sq m

Timeline

Project startedDec 2015
Proposed completionOct 2017
RERA registeredDec 2022
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

KARNATAKA HOUSING BOARD

MysoreBased in
29Projects
25Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
7,086 plotson the public record across 29 projects
64,47,758 sq mplotted area
87,06,196 sq mland declared
₹2800.90 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Local Planning AuthorityTown & Country Planning (DTCP)12 of 29 projects
BDA - Bangalore Development AuthorityUrban Development Authority2 of 29 projects
Bellary Urban Development AuthorityUrban Development Authority2 of 29 projects
Kalburgi Urban Development AuthorityUrban Development Authority2 of 29 projects
Koppal Urban Development AuthorityUrban Development Authority2 of 29 projects
BMRDA - Bangalore Metropolitan Region Development AuthorityUrban Development Authority1 of 29 projects
Gadag-Betageri Urban Development AuthorityUrban Development Authority1 of 29 projects
Haveri Urban Development AuthorityUrban Development Authority1 of 29 projects
Hubbali-Dharwad Urban Development AuthorityUrban Development Authority1 of 29 projects
Kolar Urban Development AuthorityUrban Development Authority1 of 29 projects
Madikeri Urban Development AuthorityUrban Development Authority1 of 29 projects
Mysuru Urban Development AuthorityUrban Development Authoritythis project1 of 29 projects
Tumakuru Urban Development AuthorityUrban Development Authority1 of 29 projects
Udupi Urban Development AuthorityUrban Development Authority1 of 29 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
MYSORE
District
Bengaluru Urban
Pincode
560020
Address
KENCHALAGUDU VILLAGE, JAYAPURA HOBLI
What’s nearby
Schools4 schools within 1km · 8 educational institutions within 1km · College or university 433m away
HealthcareHospital 414m away · 11 clinics within 1km · Pharmacy within 500m
LifestylePark 1.3km away · Gym or sports centre 214m away · 62+ restaurants and cafes within 1km
ShoppingSupermarket 477m away · Mall 1.3km away · Convenience store within 1km
Getting around
Expressway 2.6 kmPrimary road 19 mRailway line 412 mMetro station 403m away (Mantri Square Sampige Road)9 bus stops within 500m
Water & environment
River 281 m · VrishabhavathiWater body 295 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹233.76 Cr declared. What that works out to:

41%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Mysuru Urban Development Authority

Urban Development Authority
Building Permit

The promised possession date (31 Oct 2017) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Mysuru Urban Development Authority

Urban Development Authority

Has approved 429 RERA projectsabout 1 in 20 in Karnataka.

a plotted-layout market14% apartments · 86% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
342
On record
3,071 flats · 19,105 plots
Reach
11 taluks
Since
2017

More layout-heavy than Karnataka overall — 86% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.