Complete project overview

RERA Karnataka · Registration filing
Status
Ongoing
Land area
1,85,750 sq m
Covered area
1,85,750 sq m
Open area
27,998 sq m

Timeline

Project startedDec 2012
Proposed completionMar 2014
RERA registeredMar 2018
TodayJul 2026
02

Builder’s track record

RERA Karnataka · Promoter registration

Karnataka Housing Board

KoppalBased in
29Projects
25Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
7,086 plotson the public record across 29 projects
64,47,758 sq mplotted area
87,06,196 sq mland declared
₹2800.90 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Local Planning AuthorityTown & Country Planning (DTCP)12 of 29 projects
BDA - Bangalore Development AuthorityUrban Development Authority2 of 29 projects
Bellary Urban Development AuthorityUrban Development Authority2 of 29 projects
Kalburgi Urban Development AuthorityUrban Development Authority2 of 29 projects
Koppal Urban Development AuthorityUrban Development Authoritythis project2 of 29 projects
BMRDA - Bangalore Metropolitan Region Development AuthorityUrban Development Authority1 of 29 projects
Gadag-Betageri Urban Development AuthorityUrban Development Authority1 of 29 projects
Haveri Urban Development AuthorityUrban Development Authority1 of 29 projects
Hubbali-Dharwad Urban Development AuthorityUrban Development Authority1 of 29 projects
Kolar Urban Development AuthorityUrban Development Authority1 of 29 projects
Madikeri Urban Development AuthorityUrban Development Authority1 of 29 projects
Mysuru Urban Development AuthorityUrban Development Authority1 of 29 projects
Tumakuru Urban Development AuthorityUrban Development Authority1 of 29 projects
Udupi Urban Development AuthorityUrban Development Authority1 of 29 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Koppal
District
Koppal
Pincode
560064
Address
Behind DC office, Koppal, Behind DC office, Koppal
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.8km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 571 mPrimary road 642 mRailway line 469 mRailway station 4.2km away (Koppala)Limited bus connectivity nearby
Water & environment
Canal 76 m · Hirehalla Left Bank CanalWater body 2.5 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹14.92 Cr declared. What that works out to:

₹75/sq ftof plotted area₹803/sq m
24%of the cost is land₹18/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

Koppal Urban Development Authority

Urban Development Authority
Layout Permit

The promised possession date (31 Mar 2014) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Koppal Urban Development Authority

Urban Development Authority

Has approved 35 RERA projects0.4% of Karnataka.

a plotted-layout market0% apartments · 100% plotted layouts. Your plotted layout is this body's core business.

Builders
31
On record
0 flats · 2,717 plots
Since
2018

More layout-heavy than Karnataka overall — 100% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.