HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Units
45 units
Mix
43 × Office · 2 × Shop
Carpet area
25–124 sq mper-unit range, as filed
Floors
7
Parking
28 spaces
Land area
703 sq m
Sanctioned built-up
2,345 sq m

Timeline

RERA registeredApr 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Excavation10%
Basement (if any)10%
Plinth10%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

45 units across 10 batches
TypeArea sq mCount
Office2510
Office405
Office425
Office445
Shop1241
Shop1231
Office417
Office381
Office425
Office365

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

DREAM BUILDERS AND DEVELOPERS

PartnershipPromoter type
Nashik, MAHARASHTRABased in
3Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
45 homes · 1,580 plotson the public record across 3 projects
2,345 sq mbuilt-up filed
703 sq mland declared
₹103.87 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nashik (M Corp.)
Taluka
Nashik
District
Nashik
Pincode
422005
Survey no.
PLOT NO.03(AS PER 7/12 EXTRACT PLOT NO 3C)FINAL PLOT NO 441+442,S.NO.687/C/B/2/2B,CTS NO 7428/1
North boundary
30 FT WIDE COLONY ROAD
East boundary
PLOT NO 02
South boundary
30 MTR WIDE DP ROAD GANGAPUR ROAD
West boundary
PLOT NO 04
What’s nearby
Schools1 school within 1km · 4 educational institutions within 1km · College or university 627m away
HealthcareHospital 206m away · 5 clinics within 1km
LifestyleNo parks within 2km · 14+ restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Mall 446m away · Bank 303m away
Getting around
Expressway 1.6 kmPrimary road 6 m · Gangapur RoadNo metro or railway within 5kmLimited bus connectivity nearby
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.