HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
13
Buildings
2
Parking
126 spaces
Land area
2,000 sq m
Sanctioned built-up
7,200 sq m

Timeline

RERA registeredOct 2024
Proposed completionDec 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Electrical meter r…0%
External finishes20%
OC-readiness20%
Flat fit-out35%
Internal finishes75%
Stairs & lifts75%
Superstructure90%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

DATTADIGAMBAR ASSOCIATES

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bhosari
Taluka
Haveli
District
Pune
Pincode
411039
Survey no.
SR NO 206/2 (pt), CTS NO 4381 (pt) of Mouje-Bhosari
North boundary
PLOT OF AJIT GAVHANE AND FAMILY
East boundary
HOUSE OF AMIT WANI
South boundary
ROAD OF 12M
West boundary
PLOT OF ATUL GAVHANE
What’s nearby
Schools1 school within 500m · College or university 1.7km away
HealthcareHospital 409m away · Clinic within 2km
LifestylePark 552m away · Swimming pool within 2km
ShoppingSupermarket 491m away
Getting around
Expressway 1.1 km · Bhosari FlyoverPrimary road 177 m · Bhosari - Alandi RoadRailway line 4.6 km · Mumbai–Pune RailwayMetro station 4.5km away (Kasarwadi)Limited bus connectivity nearby
Water & environment
Water body 706 m · PCMC Water Tank
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SR NO 206/2 (pt), CTS NO 4381 (pt) of Mouje-Bhosari
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.