HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
16 units
Unit mix
15 × Commercial, 1 × Commercia
Saleable area
703–836 sq mper unit, as filed
Floors
16
Land area
3,140 sq m
Built-up area
13,111 sq m
Road widening
1,059 sq mland set aside for road widening

Timeline

RERA approvedMar 2020
Proposed completionMar 2026
TodayJul 2026
Construction progress

84% overall, as filed

Flat fit-out10%
Internal finishes60%
OC-readiness85%
External finishes90%
Podiums95%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

15 of 16 available
BuildingFloorTypeArea sq mAvailable
COMMERCIAL1Commercial7031 of 1
COMMERCIAL2Commercialmortgaged7031 of 1
COMMERCIAL3Commercialmortgaged8361 of 1
COMMERCIAL4Commercial8361 of 1
COMMERCIAL5Commercial8361 of 1
COMMERCIAL6Commercialmortgaged8361 of 1
COMMERCIAL7Commercial8361 of 1
COMMERCIAL8Commercial8361 of 1
COMMERCIAL9Commercial8361 of 1
COMMERCIAL10Commercial8361 of 1
COMMERCIAL11Commercial8361 of 1
COMMERCIAL12Commercial8361 of 1
COMMERCIAL13Commercia8360 of 1
COMMERCIAL14Commercial8361 of 1
COMMERCIAL15Commercial8361 of 1
COMMERCIAL16Commercial8361 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SUPADHA CONSTRUCTIONS PRIVATE LIMITED

OthersPromoter type
Ranga Reddy, TelanganaBased in
1Projects
1City
2020–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
OPP GACHIBOWLI POLICE STATION
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500032
North boundary
25 FEET ROAD AND N RAMA KRISHNA PROPERTY
East boundary
ROAD
South boundary
120 FEET ROAD
West boundary
NEIGHBOURS LAND
What’s nearby
SchoolsNearest school 1.0km away · College or university 1.8km away · Library 1.7km away
HealthcareHospital 1.3km away · Clinic within 2km · Doctor's clinic within 1km
LifestylePark 815m away · Gym or sports centre 860m away
ShoppingSupermarket 838m away · Bank 803m away
Getting around
Expressway 2.5 kmPrimary road 1.6 kmRailway line 1.3 kmRailway station 1.9km away (Hafeezpet)Limited bus connectivity nearby
Water & environment
Water body 567 m · Kudikunta Lake
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C20/03310/2020Survey no. 124 & 125

The promised possession date (6 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C20/03310/2020 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.