Timeline

Project startedDec 2021
RERA registeredFeb 2022
Proposed completionDec 2024
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 units across 1 batch
TypeArea sq mCount
Residential7720

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

LAXMI DEVELOPERS

PARTNERSHIP FIRMPromoter type
Junagadh, GujaratBased in
22Projects
13Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,547 homeson the public record across 22 projects
82,506 sq mbuilt-up filed
52,497 sq mland declared
₹203.83 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Urban Development AuthorityUrban Development Authority3 of 12 projects
Othersthis project3 of 12 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 12 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 12 projects
Lanja Nagar PanchayatMunicipal Council1 of 12 projects
Surat Municipal CorporationMunicipal / Corporation1 of 12 projects
Surat Urban Development AuthorityUrban Development Authority1 of 12 projects
Town Planning Authority1 of 12 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Junagadh
District
Junagadh
Address
Shreenath Nagar, Near Garbi Chowk, Giriraj Main Road, Behind Bus Stand
What’s nearby
Schools2 schools within 500m · 4 educational institutions within 1km · College or university 1.6km away
HealthcareHospital 233m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestylePark 650m away · Gym or sports centre 1.9km away · 4 restaurants and cafes within 1km
ShoppingSupermarket 525m away · Mall 864m away · ATM within 500m
Getting around
Expressway 2.5 kmPrimary road 363 mRailway line 345 m · Rajkot–SomnathRailway station 745m away (Junagadh Junction)Bus stop within 500m
Water & environment
Water body 649 m · Narsi Mehta LakeRiver 1.3 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹2.16 Cr declared to build 20 flats. What that works out to:

₹12.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹10.82 Lakhdeclared cost per flatall-in — land + construction
₹1,299/sq ftof carpet area₹13,981/sq m
25%of the cost is land₹714/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Others

Building Permitapproved 25 Feb 2022 · 4 yrs ago

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 1 block carry a Building-Use (BU) permission (latest 22 Feb 2023)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

The approving authority

The body that sanctioned this project. It has approved 2,653 RERA projects across 26 talukas about 1 in 6 in Gujarat.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.