JAI MAHADEV SMART CITY

P-OTH-17-1289 · RERA Madhya Pradesh · https://gethorizon.in/projects/jai-mahadev-smart-city-huzur-0tdfle4m

01

Complete project overview

RERA Madhya Pradesh · Registration filing
Project name
JAI MAHADEV SMART CITY
Plots
545 plots
Unit mix
545 × Plots
Revised completion
28 Nov 2021extended after an approved RERA extension
Extensions
2 approved · Covid19completion-date extension(s) granted by RERA
Quarterly reports
24 on file · latest Oct 2017 - Dec 2017quarterly progress certificates filed with RERA

Timeline

Project startedFeb 2016
RERA registeredDec 2017
Proposed completionFeb 2021
TodaySep 2026

Find your plot

Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.

545 plots across 1 batch
TypeArea sq mCount
Plots545

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Madhya Pradesh · Builder registration

MESSRS JAI MAHADEV REAL ESTATE

Partnership Firm / LLPPromoter type
4Projects
1City
2017–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
94 homes · 982 plotson the public record across 4 projects
₹43.84 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from MESSRS JAI MAHADEV REAL ESTATE— the full portfolio →

03

Location & price analysis

RERA Madhya Pradesh · Registration filing
District
Bhopal
Tehsil
Huzur
Planning area
Other
Address
Gram Neelbad , Tehsil Huzur , Bhopal
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 395m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.6 kmPrimary road 151 mRailway line 586 mRailway station 882m away (Misrod)Limited bus connectivity nearby
Water & environment
River 2.3 km · AjmarWater body 3.2 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹12.01 Cr declared to build 545 plots. What that works out to:

₹2.20 Lakhdeclared cost per plotall-in — land + construction
35%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

MP Department of Registration & Stamps

In Madhya Pradesh it’s called the collector guideline rate.

₹33,445per sq yd
₹40,000per sq m
Which rate
open plot, residential
Matched to
The rate published for “PHOENIX CORPORATE PARK”, 180 m from this project.
In force
2026-2027 schedule · effective Apr 2026

Colonies around this project

VIDYA NAGAR CHARAN 3 MAUKHYA MARG PAR₹42,000 / sq m₹35,117 / sq yd240 m
SHALIMAR FORTLEZA₹65,000 / sq m₹54,348 / sq yd350 m
SAGAR EDEN GARDEN₹38,000 / sq m₹31,773 / sq yd360 m
CHINAR INCUBE BUSSINESS CENTRE₹35,000 / sq m₹29,264 / sq yd470 m
SURENDRA LAND MARK₹48,000 / sq m₹40,134 / sq yd500 m

The same schedule, published for the places around this one — so the figure above reads in its neighbourhood, not alone.

What this number is — and isn’t

  • The minimum value Madhya Pradesh’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of colony, and says so above. How Horizon decides what to show.
05

Planning authority

RERA Madhya Pradesh · Approved building plan
Layout Permit

The promised possession date (28 Feb 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

96 plotted projects still under way within 25 km. Step out ring by ring:

Of the 394 projects the radar draws within 6 km — every kind, every stage — 54 are plotted projects still under way. This list keeps only those, and looks further out.

14 projects within 1 km — showing the nearest 6.

10 m awayPlotted Development

AAMRA NIVAASA

UJJAWALA BUILDERS AND DEVELOPERS · Bhopal · Huzur

Jul 2024registered
Feb 2029target completion
Declared cost₹28.00 CrScale171 plotsAuthorityRERA Madhya Pradesh
10 m awayPlotted Development

COURTYARD PRIME

TERRA VERDE BUILDERS AND DEVELOPERS LLP · Bhopal · Huzur

Oct 2024registered
Jul 2027target completion
Declared cost₹23.24 CrScale79 plotsAuthorityRERA Madhya Pradesh
10 m awayPlotted Development

ANADI VILLAS PHASE-2

DRAUPADI CONSTRUCTION · Bhopal · Huzur

Dec 2024registered
Jan 2029target completion
Declared cost₹6.41 CrScale12 plotsAuthorityRERA Madhya Pradesh
10 m awayPlotted Development

REGAL KASTURI PHASE-3

MS K L SHARMA AND RUKMANI SHARMA · Bhopal · Huzur

Jan 2025registered
Oct 2027target completion
Declared cost₹4.61 CrScale32 plotsAuthorityRERA Madhya Pradesh
10 m awayPlotted Development

KERWA WOODS

WHITE LOTUS · Bhopal · Huzur

Feb 2025registered
Aug 2027target completion
Declared cost₹3.32 CrScale18 plotsAuthorityRERA Madhya Pradesh
10 m awayPlotted Development

MAYFAIR PHASE - I

GLOBUS BUILDCON · Bhopal · Huzur

Sep 2025registered
Mar 2028target completion
Declared cost₹83.46 CrScale59 plotsAuthorityRERA Madhya Pradesh

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — RERA Madhya Pradesh does not publish a complaints register. This read cannot speak to them either way.