HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
20
Buildings
2
Parking
57 spaces
Land area
1,536 sq m
Sanctioned built-up
3,977 sq m

Timeline

RERA registeredMar 2025
Proposed completionApr 2028
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Community Building…0%
Solid Waste Manage…0%
Energy managemcnt0%
Fire protection an…0%
Open Parking0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREE ATHARVA APEX

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
DOMBIVLI
Taluka
Kalyan
District
Thane
Pincode
421201
Survey no.
66 HNO.4/M,E,C,G,D,B,Y AND R CTS NO. 4485 TO 4486
North boundary
ROAD
East boundary
NAV HIMALAY AND NAV PRATIMA CO OP HSG SOCIETY
South boundary
GANANAYAK CO OP HSG SOCIETY
West boundary
VIGNAHAR POOJA CO OP HSG SOCIETY
What’s nearby
Schools1 school within 500m
HealthcareHospital 318m away · 4 clinics within 1km · Pharmacy within 500m
LifestylePark 603m away · Gym or sports centre 317m away
ShoppingSupermarket 1.4km away · Bank 338m away
Getting around
Expressway 5.0 km · Kalyan RoadPrimary road 1.8 km · Kalyan - Shil RoadRailway line 353 mRailway station 1.0km away (Kopar)Limited bus connectivity nearby
Water & environment
River 205 mWater body 313 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 66 HNO.4/M,E,C,G,D,B,Y AND R CTS NO. 4485 TO 4486
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.