HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
24 units
Mix
14 × 3BHK · 7 × 2BHK · 3 × 3.5
Booked
20 of 24 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
802 sq m
Floor area
4,112 sq m
Description
LA-MAISON

Timeline

Project startedNov 2019
RERA registeredJul 2021
Proposed completionJun 2025
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

4 of 24 available
TypeArea sq mAvailable
3.51441 of 1
2BHK730 of 7
3BHK961 of 7
3BHK952 of 7
3.51400 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Sree Dhanya Homes Pvt ltd

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
9Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
502 homeson the public record across 9 projects
96,425 sq mbuilt-up filed
19,517 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation3 of 9 projects
Trivandrum Municipal CorporationMunicipal Corporationthis project3 of 9 projects
ThiruvananthapuramLocal body (LSGI)1 of 9 projects
Thiruvanathapuram Municipal CorporationMunicipal Corporation1 of 9 projects
Thrissur Muncipal Municipal CorporationMunicipal Corporation1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
ESWARAVILASAM ROAD
Village
THYCAUD
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695014
Survey no.
449/B2-1,B2, RESURVEY NO-82
Patta no.
20212,20213
What’s nearby
Schools1 school within 1km · 12 educational institutions within 1km · College or university 791m away
HealthcareHospital 157m away · 2 clinics within 1km
LifestylePark 1.0km away · Gym or sports centre 996m away · 7 restaurants and cafes within 1km
ShoppingSupermarket 756m away · Mall 746m away · Convenience store within 500m
Getting around
Expressway 3.5 kmPrimary road 730 m · Thiruvanathapuram - Thenmala RoadRailway line 394 mRailway station 1.4km away (Thiruvananthapuram Central)4 bus stops within 500m
Water & environment
River 271 m · KilliWater body 339 m
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Trivandrum Municipal Corporation

Municipal Corporation
approved 6 Nov 2019 · 6 yrs ago
Building Permit no. E6/E15/BA/46781/19Survey no. 449/B2-1,B2, RESURVEY NO-82

The promised possession date (10 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan E6/E15/BA/46781/19 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Trivandrum Municipal Corporation

Municipal corporation / municipality

Has approved 43 RERA projects2.8% of Kerala.

an apartments market81% apartments · 19% plotted layouts. Apartments like yours are this body's core business.

Builders
24
On record
1,888 flats · 188 plots
Since
2021

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.