Complete project overview

K-RERA · Registration filing
Units
28 units
Mix
28 × 3BHK
Booked
8 of 28 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,924 sq m
Floor area
7,591 sq m
Description
XXL RESIDENCY BY SREEDHANYA HOMES

Timeline

Project startedJul 2025
RERA registeredSep 2025
Proposed completionDec 2030
TodayJul 2026
Construction progress

11% overall, as filed

Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Basement(s) and Plinth75%
Excavation100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 28 available
TypeArea sq mAvailable
3BHK1358 of 10
3BHK1434 of 8
3BHK1378 of 10

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Sree Dhanya Homes Pvt ltd

CompanyPromoter type
Thrissur, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
9Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
502 homeson the public record across 9 projects
96,425 sq mbuilt-up filed
19,517 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation3 of 9 projects
Trivandrum Municipal CorporationMunicipal Corporation3 of 9 projects
ThiruvananthapuramLocal body (LSGI)1 of 9 projects
Thiruvanathapuram Municipal CorporationMunicipal Corporation1 of 9 projects
Thrissur Muncipal Municipal CorporationMunicipal Corporationthis project1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
CHIYYARAM
Village
CHIYYARAM
Taluk
Thrissur
District
Thrissur
Pincode
680026
Survey no.
303/1-8, 301/2-2
Patta no.
10699/C
What’s nearby
SchoolsNearest school 1.1km away · Library 1.0km away
HealthcareHospital 671m away · Clinic within 2km · Pharmacy within 500m
LifestylePark 1.1km away · Gym or sports centre 1.4km away
ShoppingSupermarket 971m away · Mall 1.1km away · Convenience store within 1km
Getting around
Expressway 3.8 kmPrimary road 502 m · High RoadRailway line 1.5 kmRailway station 2.6km away (Thrissur)3 bus stops within 500m
Water & environment
Canal 156 m · Peechi CanalWater body 672 m · Karamukku Kulam
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thrissur Muncipal Municipal Corporation

Municipal Corporation
approved 23 Jan 2025 · 1 yr ago
Building Permit no. KKY/BA/154/22-23Survey no. 303/1-8, 301/2-2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan KKY/BA/154/22-23 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Municipal Corporation / Municipality

A city corporation or municipality that sanctions building & development permits within its own limits. It has approved 871 RERA projects across 12 districts about 1 in 2 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.