Complete project overview

K-RERA · Registration filing
Units
99 units
Mix
56 × 3BHK · 38 × 2BHK · 5 × 4BHK
Booked
73 of 99 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
3,643 sq m
Floor area
19,959 sq m
Description
AI BY SREEDHANYA

Timeline

Project startedFeb 2022
RERA registeredMar 2022
Proposed completionDec 2028
TodayJul 2026
Construction progress

75% overall, as filed

Stilt Floor0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings75%
Electrical Fittings85%
Installation of lifts, water pumps etc85%
Fire Fighting Fittings and Equipment85%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc90%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings95%
Staircases, Lifts Wells95%
Completion of terraces floor each building95%
Overhead and Underground Water Tanks.99%
The external plumbing and external plastering99%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

26 of 99 available
TypeArea sq mAvailable
3BHK963 of 11
3BHK950 of 1
3BHK1012 of 13
3BHK1052 of 13
2BHK758 of 14
4BHK1701 of 3
4BHK1750 of 1
3BHK1040 of 1
3BHK944 of 14
2BHK742 of 11
3BHK870 of 1
4BHK1290 of 1
2BHK814 of 13
3BHK1840 of 1
3BHK970 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Sree Dhanya Homes Pvt ltd

CompanyPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
9Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
502 homeson the public record across 9 projects
96,425 sq mbuilt-up filed
19,517 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation3 of 9 projects
Trivandrum Municipal CorporationMunicipal Corporation3 of 9 projects
ThiruvananthapuramLocal body (LSGI)this project1 of 9 projects
Thiruvanathapuram Municipal CorporationMunicipal Corporation1 of 9 projects
Thrissur Muncipal Municipal CorporationMunicipal Corporation1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
KURUVANKONAM
Village
KOWDIAR
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695003
Survey no.
3122/1-4-1 3221/1,2,3,4,5,6 3224 3224/1
Patta no.
14608
What’s nearby
Schools1 school within 1km · 6 educational institutions within 1km · College or university 164m away
HealthcareHospital 1.2km away · 4 clinics within 1km
Lifestyle1 park within 500m · Gym or sports centre 467m away · 52+ restaurants and cafes within 1km
ShoppingSupermarket 412m away · Mall 383m away · Convenience store within 500m
Getting around
Primary road 62 m · Thiruvanathapuram - Thenmala RoadRailway line 3.7 kmRailway station 3.7km away (Thiruvananthapuram Central)7 bus stops within 500m
Water & environment
Water body 255 m
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Thiruvananthapuram

Local body (LSGI)
approved 9 Feb 2022 · 4 yrs ago
Building Permit no. E10/BA/82351/2019Survey no. 3122/1-4-1 3221/1,2,3,4,5,6 3224 3224/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan E10/BA/82351/2019 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thiruvananthapuram

Local body

Has approved 15 RERA projects1% of Kerala.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
13
On record
964 flats · 0 plots
Since
2021

More apartment-heavy than Kerala overall — 100% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.