01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Land area
801 sq m
Sanctioned built-up
3,288 sq m

Timeline

RERA registeredFeb 2023
Proposed completionDec 2029
TodaySep 2026
Construction progress
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Electrical meter r…0%
Podiums50%
Stilt floor50%
Stairs & lifts50%
Internal finishes55%
Basement (if any)60%
Plinth60%
Excavation70%
Superstructure85%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

HERAMB HOUSING PRIVATE LIMITED

CompanyPromoter type
Satara, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Satara
Taluka
Satara
District
Satara
Pincode
415001
Survey no.
501/A/1/3 PLOT NO 3
North boundary
9 MTRS WIDE ROAD
East boundary
PLOT NO 2
South boundary
PLOT NO 56
West boundary
7 5 MTRS WIDE ROAD
What’s nearby
Schools1 school within 1km · College or university 243m away
HealthcareHospital 194m away · 4 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Convenience store within 1km
Getting around
Expressway 3.6 kmPrimary road 787 m · Bhavani Peth RajpathNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 549 m · Mangalwar TaleCanal 2.5 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Satara Municipal Coroporation

Building Permit
Survey no. 501/A/1/3 PLOT NO 3
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

144 residential projects still under way within 25 km. Step out ring by ring:

Of the 360 projects the radar draws within 6 km — every kind, every stage — 134 are residential projects still under way. This list keeps only those, and looks further out.

14 projects within 1 km — showing the nearest 6.

SataraResidential / Group Housing

SHRI BRAMHACHAITANYA NIVAS

SHREE CHAITANYA BUILDERS

Jun 2024registered
Dec 2029target completion
Scale30 flatsAuthorityMahaRERA
SataraResidential / Group Housing

SHUBHAM PRIDE

JAYMORAYA BUILDERS

Dec 2024registered
Dec 2028target completion
Scale36 flatsAuthorityMahaRERA
SataraResidential / Group Housing

GURU ANGAN

M/S JADHAV KORATTIL PROMOTERS AND DEVELOPERS

Oct 2025registered
Dec 2030target completion
Scale48 flatsAuthorityMahaRERA
SataraResidential / Group Housing

SHIVRUDRA PRIDE

ASP GRUH PRIVATE LIMITED

Jan 2023registered
Nov 2027target completion
Scale35 flatsAuthorityMahaRERA
SataraResidential / Group Housing

VIGHNAHARTA RESIDENCY

Aniruddha Rajesh Deshmukh

Feb 2023registered
Jan 2027target completion
Scale32 flatsAuthorityMahaRERA
SataraOthers

ChandranganNiketan

Niketan Construction

Feb 2024registered
Dec 2027target completion
Scale39 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.