Complete project overview

RERA Karnataka · Registration filing
Units
7 units
Unit mix
3 × 2 BHK · 3 × 2 BHK · 1 × 3 BHK
Towers
1
Floors
4
Land area
705 sq m
Built-up area
1,615 sq m
FAR sanctioned
1.5
Covered area
326 sq m
Open area
379 sq m
Land parcels
1 survey no

Timeline

Project startedNov 2024
RERA registeredFeb 2025
Proposed completionFeb 2027
TodaySep 2026
Construction progress

30% overall, as filed

Finishing0%
Internal infra0%
External infra0%
Amenities0%
Common areas0%
Super-structure29%
Sub-structure95%
From the builder's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeCarpet sq mExclusive area sq mUndivided share sq m
1011st Floor2 BHK126.4530.6012.65
1021st Floor2 BHK125.5430.6012.60
2012nd Floor2 BHK126.4530.6012.65
2022nd Floor2 BHK125.5430.6012.60
3013rd Floor2 BHK126.4530.6012.65
3023rd Floor2 BHK125.5430.6012.60
4014th Floor3 BHK235.9811.9024.25

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes. Exclusive area is the common area allotted exclusively to the unit's owner, as the register names it. Undivided share is the portion of the land that comes with the unit, as filed — a share of the whole plot, not a demarcated piece of ground.

02

Builder’s track record

RERA Karnataka · Builder registration

TEAM ONE

Partnership FirmPromoter type
Dakshina KannadaBased in
3Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
31 homeson the public record across 3 projects
6,343 sq mbuilt-up filed
2,231 sq mland declared
₹18.01 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Mangaluru Urban Development AuthorityUrban Development Authoritythis project2 of 3 projects
Local Planning AuthorityTown & Country Planning (DTCP)1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from TEAM ONE— the full portfolio →

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Mangalore
District
Dakshina Kannada
Pincode
575012
Address
39/6P, HOSABETTU VILLAGE,SURATHKAL , MANGALORE , Mangalore , Dakshina Kannada, Karnataka - 575012
North boundary
SURVEY LINE
East boundary
PORTION OF THE SAME SURVEY NO.
South boundary
PORTION OF THE SAME SURVEY NO.
West boundary
ROAD
What’s nearby
SchoolsNo schools within 2km · College or university 906m away
HealthcareHospital 634m away · 1 clinic within 1km
LifestylePark 971m away · 4 restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Bank 415m away · ATM within 500m
Getting around
Expressway 1.0 kmPrimary road 458 mRailway line 487 m · Konkan RailwayRailway station 561m away (Surathkal)Bus stop within 500m
Water & environment
Water body 982 m
distances only — not a flood assessment
Land, title & encumbrance
LandJoint development (JDA) — built on the owner’s land by agreement
ConversionConverted to non-agricultural
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹5.51 Cr declared to build 7 flats. What that works out to:

₹78.71 Lakhdeclared cost per flatall-in — land + construction
₹3,169/sq ftof built-up area₹34,116/sq m
8%of the cost is land₹616/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Karnataka registration department

In Karnataka it’s called the guidance value.

No government guidance rate is shown for this project.

Karnataka's guidance-value gazettes are in Horizon's record, but this project's address doesn't name a place any of its sub-registrar's tables print.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RERA Karnataka · Approved building plan

Mangaluru Urban Development Authority

Urban Development Authority
approved 9 Jan 2024 · 2 yrs ago
Building Permit no. A4/BA36/2023-24(170940)Survey no. 39/6
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan A4/BA36/2023-24(170940) on the approving authority’s portal to confirm the approval.

The approving body, at scale

Mangaluru Urban Development Authority

Urban Development Authority

Has approved 440 RERA projectsabout 1 in 20 in Karnataka.

an apartments market96% apartments · 4% plotted layouts. Apartments like yours are this body's core business.

Builders
315
On record
8,036 flats · 698 plots
Reach
6 taluks
Since
2017

More apartment-heavy than Karnataka overall — 96% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Karnataka

07

Other projects nearby

The register · within 25 km

168 residential projects still under way within 25 km. Step out ring by ring:

Of the 56 projects the radar draws within 6 km — every kind, every stage — 22 are residential projects still under way. This list keeps only those, and looks further out.

6 projects within 1 km — showing the nearest 6.

570 m awayApartment

BIGAPPLE HILLS

BIGAPPLE VENTURES LLP · Mangalore

Jan 2026started
Mar 2031target completion
Declared cost₹5.40 CrScale15 flatsAuthorityRERA Karnataka
690 m awayMixed Development

KONARK HOMES

ARNAVA BUILDERS AND DEVELOPERS · Mangalore

Apr 2024started
Dec 2027target completion
Declared cost₹10.93 CrScale31 flatsAuthorityRERA Karnataka
700 m awayMixed Development

KAMMARADY ENCLAVE

MOHAMMED ABDUL RAHIMAN BYARI · Mangalore

May 2017started
Mar 2026target completion
Declared cost₹10.86 CrScale37 flatsAuthorityRERA Karnataka
720 m awayMixed Development

SPECTRUM FAH ARCADE

SPECTRUM INDIA PROPERTIES · Mangalore

Apr 2024started
Dec 2026target completion
Declared cost₹5.80 CrScale53 flatsAuthorityRERA Karnataka
970 m awayApartment

BLUEGLITZ RESIDENCE

APSATH MOHAMMED HANEEF UNHI · Mangalore

Jan 2022started
Jun 2026target completion
Declared cost₹7.75 CrScale24 flatsAuthorityRERA Karnataka
990 m awayMixed Development

ROYAL LA VISTA

ROYAL INFRATECH BUILDERS & DEVELOPERS · Mangalore

Nov 2023started
Dec 2028target completion
Declared cost₹7.47 CrScale33 flatsAuthorityRERA Karnataka

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.