HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
35
Buildings
2
Parking
151 spaces
Land area
7,055 sq m
Sanctioned built-up
28,237 sq m
Recreational open space
705 sq m

Timeline

RERA registeredNov 2022
Proposed completionDec 2029
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Stairs & lifts23%
Internal finishes32%
Superstructure94%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Puranik Builders Limited

CompanyPromoter type
Thane, MAHARASHTRABased in
18Projects
4Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,074 homeson the public record across 18 projects
2,21,938 sq mbuilt-up filed
1,32,638 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thane Municipal CorporationMunicipal Corporationthis project9 of 12 projects
Lonavala Municipal CouncilMunicipal Council2 of 12 projects
Pune Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 12 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400615
Survey no.
Survey No. Old 42 /1/Part New 55 Hissa No. 1C and 1G
North boundary
Culvert and Adjoining Plot
East boundary
Adjoining Plot and Culvert
South boundary
Adjoining plot
West boundary
20 m Road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 700m away · 1 clinic within 1km · Doctor's clinic within 1km
LifestylePark 1.8km away
ShoppingSupermarket 1.1km away
Getting around
Expressway 1.1 kmPrimary road 756 m · Kasarvadavali flyoverRailway line 2.9 kmMetro station 865m away (Gowniwada Station)Bus stop within 500m
Water & environment
River 56 mWater body 125 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Survey No. Old 42 /1/Part New 55 Hissa No. 1C and 1G
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation2 cases on record, earliest 2016
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.