Complete project overview
RAJ-RERA · Registration filing- Units
- 200 units
- Mix
- 80 × BLOCK-B GROUP HOUSING (2BHK) · 60 × BLOCK-C GROUP HOUSING (3BHK) · 60 × BLOCK-D GROUP HOUSING (2BHK)
- Carpet area
- 45–87 sq mper-type range, as filed
- Land area
- 12,781 sq m
- Completion deadline extended
- 4 extensions on record — latest to 31 Dec 2022declared reason: force majeure
- Description
- Initially, construction permission for Ground + Four Floor is obtained for Block A, B, C, D and E. Subsequently building permission for Block B, C and D were obtained for the Fifth floor to Ninth floor but as construction was not finished for Block A subsequent permission for Floor fifth to ninth is pending. Construction permission of block E is not available till the promotor ensures EWS LIG provision at any other place. The detail of separate bank account as per section 4(2)(l)(D) of the Act has been changed on 14.06.2019. As per this modification the earlier account no. 01260210002032 of UCO Bank has now been changed to account no. 37924502102 of State Bank of India Bank. W.R.T. the the Chairman Sir dated 28/11/2019 Revised maps with subsequent changes updated on 29/11/2019.As the earlier estimated finish date of Project was 31/12/2019 and w.r.t. the approval by Hon'ble Chairman dated 20/12/2019 the estimated finish date of the Project has been extended to 16/09/2020 on 20/12/2019.
Timeline
Find your flat
Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Builder’s track record
RAJ-RERA · Promoter registrationSAMBHAVNATH COMPLEX LIMITED
Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- Khasra 208,209,214 to 220,222 to 224,226,228 to 230 Plot No 01, SAVINA KHEDA, Girwa, Udaipur, 313002
- Taluka
- Girwa
- District
- Udaipur
- Pincode
- 313002
₹51.40 Cr declared to build 200 flats. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (16 Sep 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.