HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
53
Buildings
2
Parking
752 spaces
Land area
1,210 sq m
Sanctioned built-up
20,688 sq m

Timeline

RERA registeredMar 2019
Proposed completionDec 2027
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Club house Fitness…0%
2 No. of Common Ba…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Agile Real Estate Pvt. Ltd.

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
19Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
824 homeson the public record across 19 projects
3,08,533 sq mbuilt-up filed
19,058 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400607
Survey no.
New S No.79/9 Part, 83/2A Part, 83/2B/1 Part, 83/5 Part of Village Balkum
North boundary
New SNo 79-9 Pt 83-2A Pt 83-5 Pt of Village Balkum
East boundary
New S No 83-5 Part of Village Balkum
South boundary
New S No 83-2B-1 Part 83-5 part of village Balkum
West boundary
New S No 83-2A Part 83-2B-1 Part of Village Balkum
What’s nearby
SchoolsNearest school 1.6km away
HealthcareHospital 953m away · Clinic within 2km
LifestylePark 1.8km away
ShoppingSupermarket 1.5km away
Getting around
Expressway 746 m · Agra RoadPrimary road 1.6 km · Eastern Express TurnpikeRailway line 2.8 kmMetro station 1.6km away (Kapurbawdi Station)Bus stop within 1km
Water & environment
Water body 113 m · Central Lake
distances only — not a flood assessment
Legal & regulatory record
Litigation2 cases on record, earliest 2016
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 0 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.