Construction progress
Water Supply0%
Sewerage (Chamber,…0%
Water conservation…0%
Plinth90%
Excavation100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

HARI CHANDRA CONSTRUCTION

PartnershipPromoter type
Aurangabad, MAHARASHTRABased in
4Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
72 homeson the public record across 4 projects
8,400 sq mbuilt-up filed
5,505 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Aurangabad (CB)
Taluka
Aurangabad
District
Aurangabad
Pincode
431110
Survey no.
Plot No. 18 to 24 (Amalgamated), Gut No. 173 (Part), Village-Tisgaon, Nagar-I, Tq & Dist. Chhatrapati Sambhajinagar- 431102
North boundary
18.0 M Wide Road
East boundary
9.0 M Wide Road And Open Space
South boundary
Plot No. 17 And land Gut No. 173 (Part)
West boundary
15.0 M Wide D.P Road
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.1km away
HealthcareHospital 593m away · 6 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Convenience store within 1km · Bank 837m away
Getting around
Expressway 813 mRailway line 4.2 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 917 m · Kham RiverWater body 943 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. Plot No. 18 to 24 (Amalgamated), Gut No. 173 (Part), Village-Tisgaon, Nagar-I, Tq & Dist. Chhatrapati Sambhajinagar- 431102
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.