HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
11 units
Unit mix
9 × 2BHK, 2 × 3BHK
Saleable area
97–119 sq mper unit, as filed
Floors
5
Land area
836 sq m
Built-up area
1,904 sq m

Timeline

RERA approvedApr 2019
Proposed completionApr 2025
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

11 of 11 available
BuildingFloorTypeArea sq mAvailable
SILPA PRIDE12BHKmortgaged971 of 1
SILPA PRIDE12BHK971 of 1
SILPA PRIDE23BHK1191 of 1
SILPA PRIDE22BHK971 of 1
SILPA PRIDE32BHK971 of 1
SILPA PRIDE32BHK971 of 1
SILPA PRIDE43BHK1191 of 1
SILPA PRIDE42BHK971 of 1
SILPA PRIDE52BHK971 of 1
SILPA PRIDE52BHK972 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SILPA HOMES PRIVATE LIMITED

CompanyPromoter type
Hyderabad, TelanganaBased in
2Projects
1City
2019–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
16 homeson the public record across 2 projects
3,897 sq mbuilt-up filed
1,685 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Madeenaguda VILLAGE
Village
Madina Guda
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500050
North boundary
PLOT NO 123
East boundary
ROAD WIDTH 12
South boundary
ROAD WIDTH 15
West boundary
PLOT NO 137
What’s nearby
Schools2 schools within 500m · 6 educational institutions within 1km · College or university 1.7km away
HealthcareHospital 34m away · 1 clinic within 1km · Pharmacy within 500m
Lifestyle1 park within 500m · Gym or sports centre 379m away · 11+ restaurants and cafes within 1km
ShoppingSupermarket 168m away · Mall 563m away · Bank 412m away
Getting around
Expressway 60 m · Allwyn - Gangaram Road Mumbai HighwayPrimary road 1.1 kmRailway line 719 mRailway station 1.2km away (Chandanagar)Bus stop within 500m
Water & environment
Water body 674 m
distances only — not a flood assessment
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Rainwater100%
Rainwater100%
Electricity100%
Roads0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 2/C20/05527/2019Survey no. 32/1

The promised possession date (3 Apr 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 2/C20/05527/2019 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.