Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
159–164 sq mper unit, as filed
Floors
5
Land area
585 sq m
Built-up area
1,421 sq m

Timeline

RERA approvedApr 2019
Proposed completionApr 2024
TodayJul 2026
Construction progress

80% overall, as filed

Basement & plinth0%
Podiums0%
Excavation100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

8 of 10 available
BuildingFloorTypeArea sq mAvailable
SVS ROYAL OPAL13BHK1591 of 1
SVS ROYAL OPAL13BHK1641 of 1
SVS ROYAL OPAL23BHKmortgaged1641 of 1
SVS ROYAL OPAL23BHKmortgaged1590 of 1
SVS ROYAL OPAL33BHK1641 of 1
SVS ROYAL OPAL33BHK1590 of 1
SVS ROYAL OPAL43BHK1591 of 1
SVS ROYAL OPAL43BHK1641 of 1
SVS ROYAL OPAL53BHK1591 of 1
SVS ROYAL OPAL53BHK1641 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SVS INFRACON PVT LTD

CompanyPromoter type
Ranga Reddy, TelanganaBased in
6Projects
1City
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
360 homeson the public record across 6 projects
37,125 sq mbuilt-up filed
15,577 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MADINAGUDA
Village
Madina Guda
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500050
North boundary
35FT ROAD
East boundary
30FT ROAD
South boundary
PLOT NO 9
West boundary
PLOT NO 10
What’s nearby
Schools2 schools within 500m · 4 educational institutions within 1km
HealthcareHospital 62m away · Clinic within 2km · Pharmacy within 500m
LifestylePark 805m away · Gym or sports centre 994m away · 13+ restaurants and cafes within 1km
ShoppingSupermarket 166m away · Mall 1.2km away · Bank 254m away
Getting around
Expressway 45 m · Allwyn - Gangaram Road Mumbai HighwayPrimary road 462 mRailway line 942 mRailway station 1.7km away (Chandanagar)2 bus stops within 500m
Water & environment
Water body 552 m · Patel Cheruvu
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 2/C21/05540/2019Survey no. 81,82,84 & 85

The promised possession date (15 Apr 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 2/C21/05540/2019 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.