HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
15 units
Mix
11 × 3BHK · 4 × 2BHK
Booked
12 of 15 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,323 sq m
Floor area
3,435 sq m
Description
SREEROSH ORBIT

Timeline

Project startedJan 2021
RERA registeredMay 2021
Proposed completionJul 2023
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

3 of 15 available
TypeArea sq mAvailable
3BHK981 of 3
3BHK950 of 4
3BHK991 of 4
2BHK731 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

SREEROSH DEVELOPERS PVT LTD

CompanyPromoter type
Kannur, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
12Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
771 homes · 38 plotson the public record across 12 projects
1,38,554 sq mbuilt-up filed
16,688 sq mplotted area
50,254 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kannur Municipal CorporationMunicipal Corporationthis project7 of 12 projects
Chembilode Grama PanchayatGrama Panchayat1 of 12 projects
Kannur Mnicipal Municipal CorporationMunicipal Corporation1 of 12 projects
Kozhikode Municipal CorporationMunicipal Corporation1 of 12 projects
Payyannur MunicipalityMunicipality1 of 12 projects
Thalassery MunicipalityMunicipality1 of 12 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
KOTALI ROAD
Village
PUZHATHI
Taluk
Kannur
District
Kannur
Pincode
670016
Survey no.
14/121
Patta no.
3649
What’s nearby
Schools2 schools within 500m · 7 educational institutions within 1km · College or university 1.8km away
HealthcareHospital 604m away · 1 clinic within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 1.9km away
ShoppingNo supermarket within 2km · Mall 1.8km away · Bank 31m away
Getting around
Expressway 1.8 km · Kasargod-Kannur-Calicut HighwayPrimary road 4.5 km · Kannur-Calicut-Valanchery HighwayRailway line 2.8 kmRailway station 3.6km away (Kannur)Bus stop within 500m
Water & environment
Water body 743 mCanal 1.4 km · pazassi canalRiver 2.0 km
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Kannur Municipal Corporation

Municipal Corporation
approved 30 Jul 2020 · 6 yrs ago
Building Permit no. PZ.BA-58/19-20Survey no. 14/121

The promised possession date (29 Jul 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan PZ.BA-58/19-20 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kannur Municipal Corporation

Municipal corporation / municipality

Has approved 17 RERA projects1.1% of Kerala.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
7
On record
1,169 flats · 0 plots
Since
2021

More apartment-heavy than Kerala overall — 100% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.