HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
38 units
Mix
25 × 3BHK · 13 × 2BHK
Booked
29 of 38 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,620 sq m
Floor area
7,731 sq m
Description
SREEROSH SYMPHONY

Timeline

Project startedJan 2022
RERA registeredJan 2022
Proposed completionSep 2025
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

9 of 38 available
TypeArea sq mAvailable
3BHK1242 of 13
3BHK1185 of 12
2BHK822 of 13

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

SREEROSH DEVELOPERS PVT LTD

CompanyPromoter type
Kannur, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
12Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
771 homes · 38 plotson the public record across 12 projects
1,38,554 sq mbuilt-up filed
16,688 sq mplotted area
50,254 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kannur Municipal CorporationMunicipal Corporation7 of 12 projects
Chembilode Grama PanchayatGrama Panchayat1 of 12 projects
Kannur Mnicipal Municipal CorporationMunicipal Corporation1 of 12 projects
Kozhikode Municipal CorporationMunicipal Corporation1 of 12 projects
Payyannur MunicipalityMunicipalitythis project1 of 12 projects
Thalassery MunicipalityMunicipality1 of 12 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
THAYINERY
Village
PAYYANNUR
Taluk
PAYYANNUR
District
Kannur
Pincode
670307
Survey no.
26/130 (31/6)
Patta no.
3821
What’s nearby
Schools2 schools within 1km · 3 educational institutions within 1km · College or university 1.0km away
HealthcareHospital 710m away · 3 clinics within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.5km away · 11+ restaurants and cafes within 1km
ShoppingSupermarket 351m away · Mall 1.4km away · Bank 791m away
Getting around
Expressway 1.5 km · Kasargod-Kannur-Calicut HighwayRailway line 2.0 kmRailway station 4.1km away (Trikaripur)Bus stop within 1km
Water & environment
Water body 145 m · Kurinji Temple Pond, Annur
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Payyannur Municipality

Municipality
approved 27 Dec 2021 · 4 yrs ago
Building Permit no. E1-BA(329531)/2021Survey no. 26/130 (31/6)

The promised possession date (30 Sep 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan E1-BA(329531)/2021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Municipal Corporation / Municipality

A city corporation or municipality that sanctions building & development permits within its own limits. It has approved 871 RERA projects across 12 districts about 1 in 2 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.