SUKHKARTA

P99000007883 · MahaRERA · https://gethorizon.in/projects/sukhkarta-vasai-virar-city-m-9p8ebmfl

01

Complete project overview

MahaRERA · Registration filing
Project name
SUKHKARTA
Units
93 units
Floors
6
Buildings
6
Parking
3 spaces
Land area
1,750 sq m
Sanctioned built-up
1,750 sq m
Recreational open space
175 sq m

Timeline

RERA registeredAug 2017
Proposed completionJun 2021
TodaySep 2026
Construction progress
Podiums0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SUKHKARTA DEVELOPERS

PartnershipPromoter type
Palghar, MAHARASHTRABased in
2Projects
2Cities
2017–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
110 homeson the public record across 2 projects
2,908 sq mbuilt-up filed
2,207 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Sangli Miraj Kupwad City Municipal CorporationMunicipal Corporation1 of 2 projects
Vasai Virar City Municipal CorporationMunicipal Corporationthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SUKHKARTA DEVELOPERS— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Vasai-Virar City (M Corp)
Taluka
Vasai
District
Palghar
Pincode
401203
Survey no.
21/4 21/5
North boundary
S NO 22
East boundary
S NO 17
South boundary
S NO 16
West boundary
S NO 15
What’s nearby
SchoolsNearest school 1.3km away
HealthcareHospital 354m away · Clinic within 2km
LifestylePark 1.3km away
ShoppingSupermarket 1.3km away
Getting around
Primary road 2.2 kmRailway line 2.1 km · Western Railway Virar to BorivaliRailway station 2.1km away (Nalla Sopara)Limited bus connectivity nearby
Water & environment
Water body 116 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹30,017per sq yd
₹35,900per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 91 divisions of “Vasai-Virar City (M Corp)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹17,308₹69,733 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Vasai Virar City Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 21/4 21/5

The promised possession date (30 Jun 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Vasai Virar City Municipal Corporation

Municipal corporation

Has approved 627 RERA projects3.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
513
On record
8,010 flats · 60 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

1,418 residential projects still under way within 25 km. Step out ring by ring:

Of the 893 projects the radar draws within 6 km — every kind, every stage — 418 are residential projects still under way. This list keeps only those, and looks further out.

21 projects within 1 km — showing the nearest 6.

10 m awayResidential / Group Housing

SHALIBHADRA AMORA

SUMATINATH BUILDERS · Vasai-Virar City · Vasai

Aug 2017registered
Jul 2028target completion
Government Guidance Rate₹30,017/sq ydScale106 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

ANANT TOWER E AND F

SHANTINATH ENTERPRISES · Vasai-Virar City · Vasai

Apr 2018registered
Dec 2026target completion
Government Guidance Rate₹30,017/sq ydScale212 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

SHREE ANANT TOWER BUILDING NO 1

SHANTINATH ENTERPRISES · NILEMORE · Vasai

Sep 2022registered
Dec 2027target completion
Scale107 flatsAuthorityMahaRERA
10 m awayOthers

KANERI HEIGHTS

SHEKHAR BHOIR AND OTHERS · Vasai-Virar City · Vasai

Nov 2021registered
Sep 2026target completion
Government Guidance Rate₹30,017/sq ydScale179 flatsAuthorityMahaRERA
10 m awayOthers

GOLDEN ENCLAVE

GOLDEN REALTY · Vasai-Virar City · Vasai

Oct 2024registered
Dec 2026target completion
Government Guidance Rate₹30,017/sq ydScale43 flatsAuthorityMahaRERA
10 m awayOthers

GOLDEN PARADISE

DEVENDRA RISHIMUNI GUPTA · SOPARA · Vasai

Jan 2025registered
Dec 2027target completion
Scale51 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.