HORIZON
Share

SURVEY NO 162 VILLAGE KHONI TAL KALYAN

P51700016831 · MahaRERA · https://gethorizon.in/projects/survey-no-162-village-khoni-tal-kalyan-khoni-kalyan-ohh2sjey

01

Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
27
Parking
6,603 spaces
Land area
1,71,000 sq m
Sanctioned built-up
92,448 sq m
Recreational open space
38,367 sq m

Timeline

RERA registeredJun 2018
Proposed completionJan 2022
TodaySep 2026
Construction progress
Podiums0%
Aggregate area of …0%
Landscaping & Tree…50%
Street Lighting50%
Treatment And Disp…50%
Solid Waste Manage…50%
Water conservation…50%
Fire protection an…50%
Internal Roads & F…55%
Water Supply55%
Sewerage (Chamber,…55%
Storm Water Drains55%
Electrical meter r…60%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY

Public AuthorityPromoter type
Mumbai Suburban, MAHARASHTRABased in
11Projects
4Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
11,073 homes · 288 plotson the public record across 11 projects
3,62,309 sq mbuilt-up filed
62,500 sq mplotted area
6,98,710 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Maharashtra Housing and Area Development Authority (MHADA)Housing Authoritythis project2 of 3 projects
Executive Engineer B P Cell Pradhan Mantri Aawas Yozana1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Khoni
Taluka
Kalyan
District
Thane
Pincode
421301
Survey no.
162
North boundary
FOREST LAND
East boundary
DHAMTAN VILLEGE
South boundary
KHONI VILLAGE
West boundary
FOREST LAND
What’s nearby
SchoolsNearest school 1.3km away
HealthcareHospital 1.6km away · Clinic within 2km
LifestylePark 1.1km away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.5 km · Kalyan-Murbad RoadPrimary road 1.7 km · Agra RoadRailway line 3.3 km · Central LineRailway station 3.3km away (Kalyan Junction)Limited bus connectivity nearby
Water & environment
River 1.5 km · UlhasWater body 2.3 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. 162

The promised possession date (9 Jan 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

2,638 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,284 projects the radar draws within 6 km — every kind, every stage — 514 are residential projects still under way. This list keeps only those, and looks further out.

14 projects within 1 km — showing the nearest 6.

adharwadiResidential / Group Housing

RAUNAK CITY SECTOR IV - D9

RAUNAK CORPORATION

Aug 2018registered
Dec 2027target completion
Scale128 flatsAuthorityMahaRERA
adharwadiMixed

EARTH PARK BUILDING NO 1

AASTHA HOUSING CORPORATION

Sep 2025registered
Dec 2031target completion
Scale122 flatsAuthorityMahaRERA
Kalyan-DombivaliResidential / Group Housing

Heaven Enclave

Saxena Dreams Realty LLP

Jul 2025registered
Dec 2026target completion
Government Guidance Rate₹49,415/sq ydScale19 flatsAuthorityMahaRERA
Kalyan-DombivaliResidential / Group Housing

BILESHWAR

ASHAPURA COMBINES

Feb 2024registered
Dec 2028target completion
Government Guidance Rate₹49,415/sq ydScale291 flatsAuthorityMahaRERA
Kalyan-DombivaliResidential / Group Housing

VISHWANATH DARSHAN

ASHAPURA COMBINES

Dec 2023registered
Dec 2029target completion
Government Guidance Rate₹49,415/sq ydScale216 flatsAuthorityMahaRERA
Kalyan-DombivaliOthers

NARMADESHWAR

ASHAPURA COMBINES

Jun 2024registered
Dec 2030target completion
Government Guidance Rate₹49,415/sq ydScale101 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.