Timeline

RERA registeredMar 2022
Proposed completionDec 2026
TodayJul 2026
Construction progress
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Energy managemcnt100%
Fire protection an…100%
Electrical meter r…100%
Aggregate area of …100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ACE GLOBAL REALTY

PartnershipPromoter type
Pune, MAHARASHTRABased in
5Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
5 projectson the public record across 5 projects
27,515 sq mbuilt-up filed
13,950 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kiwale
Taluka
Haveli
District
Pune
Pincode
412101
Survey no.
88/4,88/10/1,88/10/2,88/11,88/16/1,88/17+18/1,87/B KIWALE
North boundary
Proposed Ace Abode Wing D
East boundary
Part of S No 88
South boundary
Part of S No 87B and Ace Abode Wing B
West boundary
Part of S No 88 and Ace Abode Wing A and B Wing
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 539m away · 1 clinic within 1km · Pharmacy within 500m
LifestylePark 852m away · 14+ restaurants and cafes within 1km
ShoppingSupermarket 928m away · Convenience store within 1km · ATM within 500m
Getting around
Expressway 713 mPrimary road 713 mRailway line 2.3 km · Mumbai–Pune RailwayRailway station 3.0km away (Dehu Road)Limited bus connectivity nearby
Water & environment
River 761 m · Pavana
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 88/4,88/10/1,88/10/2,88/11,88/16/1,88/17+18/1,87/B KIWALE
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.