Complete project overview

MahaRERA · Registration filing
Units
114 units
Mix
54 × 2 BHK · 36 × 1 BHK · 18 × 3 BHK · 6 × Shop
Carpet area
17–87 sq mper-unit range, as filed
Floors
7
Buildings
3
Parking
38 spaces
Land area
3,800 sq m
Sanctioned built-up
8,355 sq m

Timeline

RERA registeredJul 2023
Proposed completionDec 2027
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Street Lighting0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

114 units across 9 batches
TypeArea sq mCount
3 BHK871
3 BHK8317
1 BHK5218
Shop172
Shop262
Shop352
2 BHK6753
2 BHK711
1 BHK5018

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

ADITYA PROMOTERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
4Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
324 homeson the public record across 4 projects
58,552 sq mbuilt-up filed
23,938 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Jalochi
Taluka
Baramati
District
Pune
Pincode
413102
Survey no.
GAT NO 134/3/1/1/1/1/1/1
North boundary
URBAN GRAM
East boundary
12 MTR ROAD
South boundary
7 MTR INTERNAL ROAD
West boundary
PART OF GAT NO 135
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.5 kmPrimary road 1.9 kmRailway line 2.4 kmRailway station 3.1km away (Baramati)Limited bus connectivity nearby
Water & environment
Canal 853 mWater body 1.8 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.