ASMA TOWER

PM1270002501288 · MahaRERA · https://gethorizon.in/projects/asma-tower-neral-karjat-q9lcn8tx

01

Complete project overview

MahaRERA · Registration filing
Units
32 units
Floors
8
Buildings
2
Parking
48 spaces
Land area
617 sq m
Sanctioned built-up
1,382 sq m

Timeline

RERA registeredOct 2025
Proposed completionDec 2029
TodaySep 2026
Construction progress
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Street Lighting0%
Fire protection an…0%
Aggregate area of …0%
Open Parking0%
Superstructure20%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

MUJEEB BADRUDDIN ANSARI

IndividualPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Neral
Taluka
Karjat
District
Raigarh
Pincode
410101
Survey no.
Survey No. 174, Plot No. 03(Old Plot No.3, S No. 67/1A/2B)
North boundary
Plot No. 1,2
East boundary
28 mtr state highway
South boundary
Plot No. 4
West boundary
H No. 01 (Open Plot)
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.1km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 706 m · Karjat RoadRailway line 990 m · Mumbai-Pune RailwayRailway station 1.5km away (Neral Junction)Limited bus connectivity nearby
Water & environment
Water body 730 mRiver 783 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Raigarh Zilla Parishad Alibaug

Building Permit
Survey no. Survey No. 174, Plot No. 03(Old Plot No.3, S No. 67/1A/2B)
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

1,280 residential projects still under way within 25 km. Step out ring by ring:

Of the 314 projects the radar draws within 6 km — every kind, every stage — 75 are residential projects still under way. This list keeps only those, and looks further out.

16 projects within 1 km — showing the nearest 6.

50 m awayResidential / Group Housing

KAILASH COMPLEX PHASE 2

BRAMHA CONSTRUCTIONS · Mamdapur · Karjat

Mar 2024registered
Mar 2027target completion
AuthorityMahaRERA
50 m awayMixed

ARENA ONE

TECTRA ENGINEERING · Mamdapur · Karjat

Aug 2026registered
Dec 2028target completion
Scale46 flatsAuthorityMahaRERA
50 m awayResidential / Group Housing

TOWER C-MARS,PLUTO

DREAMZ REALTY · Neral · Karjat

Jul 2023registered
Dec 2030target completion
Scale96 flatsAuthorityMahaRERA
70 m awayResidential / Group Housing

SUKOON RESIDENCY

RIFAA STRUCTURAL SOLUTIONS PRIVATE LIMITED · Mamdapur · Karjat

Jun 2022registered
Jun 2027target completion
Scale77 flatsAuthorityMahaRERA
330 m awayMixed

Manaya Residency

Manaya Developers · Mamdapur · Karjat

Dec 2025registered
Dec 2028target completion
Scale61 flatsAuthorityMahaRERA
340 m awayOthers

ZAINAB HEIGHTS

SHALIN DEVELOPERS · Mamdapur · Karjat

Jun 2024registered
Dec 2026target completion
Scale33 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.