Gokul Dham

P52000008816 · MahaRERA · https://gethorizon.in/projects/gokul-dham-mamdapur-karjat-32dqba9s

Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Project name
Gokul Dham
Units
218 units
Floors
6
Buildings
14
Parking
7 spaces
Land area
6,390 sq m
Sanctioned built-up
6,895 sq m
Recreational open space
639 sq m

Timeline

RERA registeredAug 2017
Proposed completionJun 2021
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

Riddhi Infra

PartnershipPromoter type
Thane, MAHARASHTRABased in
2Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
235 homeson the public record across 2 projects
8,132 sq mbuilt-up filed
6,873 sq mland declared
₹3.22 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Others1 of 2 projects
Raigad Zilla Parishad Alibagthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Riddhi Infra— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Mamdapur
Taluka
Karjat
District
Raigarh
Pincode
410101
Survey no.
36/1C, 35/1D
North boundary
18 m Wide Road
East boundary
Railway Line
South boundary
Sr No 58 and 61 hissa 2
West boundary
Sr No 35-2
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 540m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 202 m · Karjat RoadRailway line 723 m · Mumbai-Pune RailwayRailway station 880m away (Neral Junction)Limited bus connectivity nearby
Water & environment
Water body 477 mRiver 563 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Raigad Zilla Parishad Alibag

Building Permit
Survey no. 36/1C, 35/1D

The promised possession date (30 Jun 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Raigad Zilla Parishad Alibag

Planning authority

Has approved 15 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
15
On record
70 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

1,213 residential projects still under way within 25 km. Step out ring by ring:

Of the 335 projects the radar draws within 6 km — every kind, every stage — 74 are residential projects still under way. This list keeps only those, and looks further out.

18 projects within 1 km — showing the nearest 6.

250 m awayResidential / Group Housing

ELCARIM ENCLAVE

ELCARIM DEVELOPERS AND PROPERTIES PRIVATE LIMITED · Mamdapur · Karjat

Apr 2024registered
Dec 2026target completion
Scale91 flatsAuthorityMahaRERA
300 m awayOthers

BURHAN HEIGHTS

BURHAN BUILDERS AND DEVELOPERS · Mamdapur · Karjat

Feb 2022registered
Dec 2026target completion
Scale100 flatsAuthorityMahaRERA
490 m awayResidential / Group Housing

Tower A Mercury, Venus

DREAMZ REALTY · Neral · Karjat

Feb 2023registered
Dec 2030target completion
Scale88 flatsAuthorityMahaRERA
490 m awayResidential / Group Housing

Tower B-Jupiter, Neptune

DREAMZ REALTY · Neral · Karjat

May 2023registered
Dec 2030target completion
AuthorityMahaRERA
530 m awayResidential / Group Housing

MULLA RESIDENCY

Zafar Mohd Rashid Mulla · Neral · Karjat

Mar 2024registered
Dec 2026target completion
Scale21 flatsAuthorityMahaRERA
540 m awayOthers

DIVINE CAPITAL

DHARTI ASSOCIATES · Dhamote · Karjat

May 2019registered
Dec 2028target completion
Government Guidance Rate₹41,054/sq ydScale113 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.