Complete project overview

UP-RERA · Registration filing
Land area
1,216 sq m

Timeline

Project startedDec 2022
RERA registeredJan 2023
Proposed completionDec 2024
TodayJul 2026
02

Builder’s track record

UP-RERA · Promoter registration

M/S SHALIMAR KSMB PROJECTS; KSM BASHIR MOHD & SONS; REHANA FAROOQUI; S.A. INFRABUILD PRIVATE LIMITED

Partnership FirmPromoter type
12Registered projects
1Projects
1City
2023–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Lucknow
Tehsil
Lucknow
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 837m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 689 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.4 km · Gomti RiverWater body 1.9 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹9.78 Cr declared. What that works out to:

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan

Lucknow Development Authority

Development Authority
approved 13 Oct 2022 · 3 yrs ago
Building Permit no. Row House/06006/LDA/BP/22-23/1602/30082022

The promised possession date (15 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record (dated 2 Dec 2024)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

Verify it yourself — look up plan Row House/06006/LDA/BP/22-23/1602/30082022 on the approving authority’s portal to confirm the sanction.

Complaints register

1 complaint on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.