Dhanalaxmi Chambers Premises Co Op Soc. Ltd

PC1330002500427 · MahaRERA · https://gethorizon.in/projects/dhanalaxmi-chambers-premises-co-op-soc-thane-m-corp-hwc8vm3d

01

Complete project overview

MahaRERA · Registration filing
Units
85 units
Floors
9
Buildings
2
Parking
80 spaces
Land area
1,210 sq m
Sanctioned built-up
5,379 sq m

Timeline

RERA registeredJul 2025
Proposed completionDec 2027
TodaySep 2026
Construction progress
Podiums0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
OC-readiness30%
Flat fit-out50%
External finishes60%
Superstructure80%
Internal finishes80%
Stairs & lifts80%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SHRUSTI NX

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400601
Survey no.
CTS No.317, Sector No. Delapitated Sector-2 of Mouje-Chendani
North boundary
GHOKHALE ROAD FROM THANE STATION
East boundary
PROPERTY OF CITY SURVEY NO 338
South boundary
PROPERTY OF CITY SURVEY NO 342 & 343
West boundary
PROPERTY OF CITY SURVEY NO 316 & 344
What’s nearby
SchoolsNearest school 1.8km away · 5 educational institutions within 1km · College or university 418m away
HealthcareHospital 29m away · 12 clinics within 1km · Pharmacy within 500m
Lifestyle2 parks within 500m · Gym or sports centre 1.0km away · 28+ restaurants and cafes within 1km
ShoppingSupermarket 718m away · Bank 489m away · ATM within 500m
Getting around
Expressway 1.2 kmPrimary road 834 m · Lal Bahadur Shastri MargRailway line 197 mRailway station 174m away (Thane)12 bus stops within 500m
Water & environment
Water body 300 m · Hariyali Talao
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹60,034per sq yd
₹71,800per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 101 divisions of “Thane (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹26,923₹1,55,185 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. CTS No.317, Sector No. Delapitated Sector-2 of Mouje-Chendani
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

280 commercial projects still under way within 25 km. Step out ring by ring:

Of the 1,617 projects the radar draws within 6 km — every kind, every stage — 61 are commercial projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

890 m awayCommercial

SHIV HEIGHTS

SARWANGKRIPA DEVELOPERS LLP · Thane

Feb 2022registered
Dec 2026target completion
Government Guidance Rate₹60,034/sq ydScale79 flatsAuthorityMahaRERA
900 m awayCommercial

Rhythm

Aradhana Lifespace LLP · Thane

May 2020registered
Jun 2026target completion
Government Guidance Rate₹60,034/sq ydScale77 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.