01
Complete project overview
MahaRERA · Registration filing- Floors
- 2
- Parking
- 43 spaces
- Land area
- 20,990 sq m
- Sanctioned built-up
- 6,418 sq m
- Recreational open space
- 2,114 sq m
Timeline
RERA registeredFeb 2023
Proposed completionMar 2026
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Podiums0%
Storm Water Drains0%
Energy managemcnt0%
Aggregate area of …0%
Open Parking0%
OC-readiness50%
Water Supply50%
Flat fit-out60%
Stairs & lifts60%
Street Lighting60%
Water conservation…60%
Electrical meter r…60%
External finishes75%
Treatment And Disp…75%
Solid Waste Manage…75%
Internal finishes80%
Sewerage (Chamber,…80%
Internal Roads & F…90%
Landscaping & Tree…90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
02
Builder’s track record
MahaRERA · Promoter registrationDOODLE HOMES LLP
PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2023–2026Active
Timelineevery project, start → promised completion
The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Sadapur
- Taluka
- Mawal
- District
- Pune
- Pincode
- 410401
- Survey no.
- 7/3 Part , 7/4/A & 7/4/C Part
- North boundary
- S NO 66 AND S NO 7-4 Part
- East boundary
- S NO 14
- South boundary
- S NO 7-3 P AND 7-4 P
- West boundary
- S NO 7-2
What’s nearby
Schools1 school within 500m · 11 educational institutions within 1km · College or university 916m away
HealthcareHospital 145m away · 19 clinics within 1km · Doctor's clinic within 1km
LifestylePark 566m away · Gym or sports centre 736m away · 18+ restaurants and cafes within 1km
ShoppingSupermarket 899m away · Convenience store within 1km · Bank 289m away
Getting around
Expressway 75 m · Shivaji RoadPrimary road 856 m · Kamgar PutalaRailway line 783 mMetro station 321m away (Kasba Peth)13 bus stops within 500m
Water & environment
Water body 139 m
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.