Complete project overview

RAJ-RERA · Registration filing
Plots
88 plots
Land area
16,990 sq m
Completion deadline extended
1 extension on record — latest to 20 Feb 2025declared reason: other than force majeure
Description
12 Plots (Plot No. 23-34) having Total area of 1497.35 Sq. mtrs equal to 12.5% have been kept as mortgage under Ajmer Development Authority. These plots would be allotted after the internal development work of project is completed and development charges are deposited with Ajmer Development Authority.

Timeline

Construction startFeb 2023
RERA registeredMay 2023
Proposed completionDec 2024
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

88 plots across 43 batches
TypeArea sq mCount
Plot12835
Plot1285
Plot1281
Plot1294
Plot1285
Plot1221
Plot1781
Plot951
Plot951
Plot1151
Plot981
Plot991
Plot1101
Plot1001
Plot1131
Plot1231
Plot1261
Plot961
Plot1291
Plot1541
Plot1281
Plot1111
Plot951
Plot1561
Plot1601
Plot951
Plot971
Plot1131
Plot951
Plot1181
Plot1051
Plot1071
Plot1091
Plot2001
Plot1401
Plot1031
Plot1101
Plot1641
Plot1111
Plot1481
Plot1321
Plot1241
Plot1071

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

G S DREAMHOME LLP

OrganisationPromoter type
Ajmer, RajasthanBased in
8Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
397 homes · 711 plotson the public record across 8 projects
55,422 sq mbuilt-up filed
3,22,117 sq mplotted area
3,61,509 sq mland declared
₹173.59 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ajmer Development AuthorityDevelopment Authoritythis project4 of 6 projects
Urban Improvement TrustUrban Improvement Trust2 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
1293, Ansal Township, Janana Hospital Road, Makarwali, Ajmer, Ajmer, 305004
Village
Makarwali
Taluka
Ajmer
District
Ajmer
Pincode
305004
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 266m away · Clinic within 2km
LifestyleNo parks within 2km · 4 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Mall 1.2km away
Getting around
Expressway 2.8 km · Pushkar RoadPrimary road 2.2 kmRailway line 4.2 kmRailway station 4.0km away (Budha Pushkar)Limited bus connectivity nearby
Water & environment
Water body 270 mCanal 3.3 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹7.40 Cr declared to build 88 plots. What that works out to:

₹8.41 Lakhdeclared cost per plotall-in — land + construction
₹405/sq ftof plotted area₹4,356/sq m
46%of the cost is land₹186/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Ajmer Development Authority

Development Authority
Layout Permitapproved 1 May 2023 · 3 yrs ago

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Ajmer Development Authority

Development authority

Has approved 51 RERA projects2.3% of Rajasthan.

a plotted-layout market16% apartments · 84% plotted layouts. Your plotted layout is this body's core business.

Builders
40
On record
990 flats · 3,829 plots
Reach
4 districts
Since
2017

More layout-heavy than Rajasthan overall — 84% plots here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.