01

Complete project overview

MahaRERA · Registration filing
Units
235 units
Floors
10
Buildings
6
Parking
51 spaces
Land area
4,150 sq m
Sanctioned built-up
9,797 sq m

Timeline

RERA registeredSep 2023
Proposed completionDec 2026
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Storm Water Drains0%
Landscaping & Tree…0%
Electrical meter r…0%
Water Supply10%
Internal Roads & F…15%
Sewerage (Chamber,…15%
OC-readiness20%
Street Lighting20%
Flat fit-out60%
Stairs & lifts60%
External finishes70%
Internal finishes90%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Fia Developers Pvt. Ltd.

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
9Projects
1City
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
598 homeson the public record across 9 projects
24,453 sq mbuilt-up filed
10,637 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Collector Office PalgharCollector office6 of 8 projects
Palghar Municipal CouncilMunicipal Councilthis project1 of 8 projects
Town Planning And Valuation Department, Assistant Director Of Town Planning, Branch Palghar1 of 8 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Fia Developers Pvt. Ltd.— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Palghar
Taluka
Palghar
District
Palghar
Pincode
401404
Survey no.
SURVEY NO. 101/1/B
North boundary
SURVEY NO 101
East boundary
SURVEY NO 18
South boundary
7 MTR LAYOUT ROAD
West boundary
18 MTR LAYOUT ROAD
What’s nearby
SchoolsNearest school 1.0km away
HealthcareHospital 179m away · 4 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 49m away
Getting around
Expressway 1.1 kmPrimary road 813 mRailway line 255 mRailway station 247m away (Palghar)Limited bus connectivity nearby
Water & environment
Water body 665 m · Water TankRiver 2.2 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹29,766per sq yd
₹35,600per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Palghar”.
In force
2026-2027 schedule
Spread
₹18,813₹41,556 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Palghar Municipal Council

Municipal Council
Building Permit
Survey no. SURVEY NO. 101/1/B
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Palghar Municipal Council

Municipal corporation

Has approved 94 RERA projects0.5% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
86
On record
209 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

361 residential projects still under way within 25 km. Step out ring by ring:

Of the 597 projects the radar draws within 6 km — every kind, every stage — 172 are residential projects still under way. This list keeps only those, and looks further out.

79 projects within 1 km — showing the nearest 6.

10 m awayResidential / Group Housing

Nisarg Shrushti Phase-2

Arvel Realtors · Tembhode · Palghar

Oct 2019registered
Nov 2026target completion
Scale51 flatsAuthorityMahaRERA
10 m awayMixed

ROMAN RESIDENCY

Shantee Housing · Vasai-Virar City · Vasai

Aug 2021registered
Dec 2027target completion
Government Guidance Rate₹30,017/sq ydScale3 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

SAMAIRA RESIDENCY

AV CRYSTAL SPACE · Vasai-Virar City · Vasai

Jan 2022registered
Dec 2026target completion
Government Guidance Rate₹30,017/sq ydScale109 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

Gopikisan Patil Complex Bldg No 1

SUMATINATH ENTERPRISES · Chandrapada · Vasai

Dec 2021registered
Dec 2027target completion
Government Guidance Rate₹37,375/sq ydScale197 flatsAuthorityMahaRERA
10 m awayResidential / Group Housing

SAI ENCLAVE BUILDING NO.2

M/S. RADHEYA CONSTRUCTION COMPANY · Tivari · Vasai

May 2022registered
Dec 2029target completion
Government Guidance Rate₹50,753/sq ydAuthorityMahaRERA
10 m awayOthers

JK HERITAGE

VAILANKANNI REALTORS · VASAI · Vasai

Sep 2022registered
Dec 2027target completion
Scale6 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.