HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
10
Buildings
2
Parking
8 spaces
Land area
452 sq m
Sanctioned built-up
1,427 sq m

Timeline

RERA registeredApr 2022
Proposed completionMar 2026
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Meera Developers

PartnershipPromoter type
Thane, MAHARASHTRABased in
9Projects
6Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
247 homes · 339 plotson the public record across 9 projects
18,539 sq mbuilt-up filed
10,637 sq mland declared
₹61.13 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
DepalpurTown & Country Planning (DTCP)2 of 8 projects
Rajkot Municipal CorporationMunicipal / Corporation2 of 8 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 8 projects
Kulgaon Badlapur Municipal CouncilMunicipal Councilthis project1 of 8 projects
SUDA/SMC1 of 8 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 8 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Badlapur (M Cl)
Taluka
Ambarnath
District
Thane
Pincode
421503
Survey no.
Survey No 34-1/12, Hissa No. 3, Plot No. 7
North boundary
06m Wide Road
East boundary
Swayambhu CHS
South boundary
Bunglow
West boundary
12m Wide Road
What’s nearby
SchoolsNo schools within 2km · Library 521m away
HealthcareHospital 315m away · 1 clinic within 1km · Pharmacy within 500m
Lifestyle1 park within 500m · 5 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Convenience store within 1km · Bank 398m away
Getting around
Primary road 495 m · MIDC RoadRailway line 608 m · Mumbai-Pune RailwayRailway station 590m away (Badlapur)3 bus stops within 500m
Water & environment
Water body 640 m · Gaodevi Lake
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kulgaon Badlapur Municipal Council

Municipal Council
Building Permit
Survey no. Survey No 34-1/12, Hissa No. 3, Plot No. 7

The promised possession date (31 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kulgaon Badlapur Municipal Council

Municipal corporation

Has approved 119 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
102
On record
860 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.