Detailed Report

KRUPA RESIDENCY

PM1280002503049 · MahaRERA · https://gethorizon.in/projects/krupa-residency-zadgaon-ct-ratnagiri-tnqdtdbn

01

Complete project overview

MahaRERA · Registration filing
Units
19 units
Floors
7
Buildings
2
Parking
33 spaces
Land area
590 sq m
Sanctioned built-up
1,485 sq m

Timeline

RERA registeredMar 2026
Proposed completionJun 2027
TodaySep 2026
Construction progress
Flat fit-out0%
External finishes0%
OC-readiness0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Internal finishes10%
Water Supply10%
Stairs & lifts25%
Superstructure40%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Kedar Constructions

Proprietorship/ConcernPromoter type
Ratnagiri, MAHARASHTRABased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
The Horizon Radar(within 6 km)
2km4km6kmN
  • This project
  • 18 new projects last year
  • 273 nearby projects
1 km radius · coordinates as filed · 16.9898, 73.3135 · © OpenStreetMap contributors
Village
Zadgaon CT
Taluka
Ratnagiri
District
Ratnagiri
Pincode
415612
Survey no.
CTS No 715/42 S. No. 370/A1A1A1A1A1/B PART
North boundary
Municipal Road
East boundary
Land of CTS No 715
South boundary
Streamlet and Land of CTS No 713
West boundary
Land of CTS No 715
What’s nearby
SchoolsNearest school 1.4km away · College or university 1.9km away
HealthcareHospital 131m away · 3 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 381m away · 6 restaurants and cafes within 1km
ShoppingSupermarket 1.1km away · Bank 205m away
Getting around
Expressway 798 m · Hodekar RoadPrimary road 27 mRailway line 3.3 kmRailway station 5.0km away (Ratnagiri)Bus stop within 500m
Water & environment
River 1.8 km · Kajvi
distances only — not a flood assessment
04

Satellite view of the site

Google Open Buildings, 2016–2023 · Sentinel-2 imagery

A building already stood within ~20 m of the recorded location in 2016 — before this project started in 2026. The yearly view ends in 2023, so it does not cover this project's own construction; see the 2026 image.

Satellite view, year by year

loading 2023

Height estimated by a model from satellite imagery — not a survey, and the series ends in 2023. The dashed shape is within ~20 m of the filed location.

Satellite photographs of the same ground

Feb 2017
Mar 2023
Feb 2026

Sentinel-2, 10 m per pixel — about 400 m of ground across. Each frame is one dry-season day, so haze can dull a site.

How to read this

  • A building is first visible in 2016.
  • This state publishes a point, not a plot outline, so the shape is a circle around it. A neighbour’s building can fall inside.
  • Site is a ~20 m circle around the RERA point, not a plot outline: buildings inside it may belong to neighbours.
  • The yearly site view ends in 2023, before this project started in 2026.

Google Open Buildings 2.5D Temporal (CC BY 4.0) · Contains modified Copernicus Sentinel data 2017–2026

05

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

06

Planning authority

MahaRERA · Approved building plan

Ratnagiri Municipal Council

Municipal Council
Building Permit
Survey no. CTS No 715/42 S. No. 370/A1A1A1A1A1/B PART
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Ratnagiri Municipal Council

Municipal corporation

Has approved 29 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
26
On record
345 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

08

Other projects nearby

The register · within 25 km

86 residential projects still under way within 25 km. Step out ring by ring:

Of the 273 projects the radar draws within 6 km — every kind, every stage — 74 are residential projects still under way. This list keeps only those, and looks further out.

32 projects within 1 km — showing the nearest 6.

10 m awayResidential / Group Housing

Kalpavriksha Heritage

Kalpavriksha Builders & Developers · Ratnagiri

May 2020registered
Jun 2027target completion
Government Guidance Rate₹29,014/sq ydScale226 flatsAuthorityMahaRERA
110 m awayResidential / Group Housing

SHRIHARI SANKUL

SAUKHYAM BUILDERS PRIVATE LIMITED · Nachane · Ratnagiri

Feb 2024registered
Mar 2027target completion
Scale21 flatsAuthorityMahaRERA
110 m awayResidential / Group Housing

UNITY ASTER

UNITYMEGACORPPVTLTD · Nachane · Ratnagiri

May 2024registered
Dec 2028target completion
Scale65 flatsAuthorityMahaRERA
160 m awayOthers

ARIHANT PRIME

ARIHANT DREAM HOMES PVT LTD · Padavewadi · Ratnagiri

Aug 2021registered
Dec 2026target completion
Government Guidance Rate₹23,830/sq ydScale146 flatsAuthorityMahaRERA
160 m awayResidential / Group Housing

ARIHANT THE PARK PHASE - I

RATNAGIRI DREAM HOMES PVT. LTD. · Tiwandewadi · Ratnagiri

Sep 2021registered
Dec 2027target completion
Scale309 flatsAuthorityMahaRERA
160 m awayResidential / Group Housing

Saffron

Mohsin Salim Memon · Chiplun

Apr 2022registered
Dec 2026target completion
Government Guidance Rate₹29,181/sq ydScale20 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.

Sources

Where each section of this report comes from.

  1. 01Complete project overview
    • The project's registration filing with MahaRERA, as the builder submitted it.
  2. 02Builder's track record
    • MahaRERA: the builder's registration.
    • The track record: every project filed under this builder, counted by Horizon across the state RERA registers it holds.
  3. 03Location
    • Address and pincode: the MahaRERA filing.
    • Coordinates: as filed with MahaRERA.
    • What's nearby and getting around: distances measured by Horizon on OpenStreetMap data, © OpenStreetMap contributors (ODbL). Not from the RERA filing.
    • The Horizon Radar: the RERA-registered projects Horizon holds within 6 km of these coordinates.
    • Map: © OpenStreetMap contributors (ODbL).
  4. 04Satellite view of the site
    • Building footprint and height by year: Google Open Buildings 2.5D Temporal (CC BY 4.0), a model estimate of building presence and height from satellite imagery.
    • Photographs: Copernicus Sentinel-2 imagery (contains modified Copernicus Sentinel data 2017–2026).
  5. 05Government Guidance Rate
    • No government guidance rate could be matched to this project from Maharashtra's published schedules.
  6. 06Planning authority
    • MahaRERA: the approved building plan, as filed.
    • The approving body's other projects: counted by Horizon across the register.
  7. 07Complaints & litigation
    • MahaRERA's public record lists no complaints or litigation for this project.
  8. 08Other projects nearby
    • The RERA-registered projects Horizon holds within 25 km of these coordinates.

Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/krupa-residency-zadgaon-ct-ratnagiri-tnqdtdbn.

Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.