Complete project overview

RERA Karnataka · Registration filing
Project name
M S IMMANUEL RESIDENCIES
Land area
465 sq m
Covered area
302 sq m
Open area
163 sq m

Timeline

Project startedJan 2021
RERA registeredApr 2021
Proposed completionDec 2022
TodaySep 2026
02

Builder’s track record

RERA Karnataka · Builder registration

M S DEVELOPERS AND CONSTRUCTIONS

Bengaluru UrbanBased in
2Projects
1City
2021–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
836 sq mland declared
₹6.40 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from M S DEVELOPERS AND CONSTRUCTIONS— the full portfolio →

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Bengaluru East
District
Bengaluru Urban
Pincode
560043
Address
Site Nos.7 and 8, Present BBMP Katha No.180/194/2, Comprised in Property No.92/4B, situated at Horamavu Agara Village, K.R.Puram Hobli
What’s nearby
SchoolsNearest school 1.5km away
HealthcareHospital 764m away · 6 clinics within 1km · Pharmacy within 500m
LifestylePark 1.7km away · Gym or sports centre 311m away · 5 restaurants and cafes within 1km
ShoppingSupermarket 366m away
Getting around
Expressway 1.8 km · Old Madras RoadPrimary road 1.7 km · Whitefield RoadRailway line 1.3 kmRailway station 1.3km away (Hoodi)Bus stop within 1km
Water & environment
Water body 665 m · Basavanapura Kere
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹4.00 Cr declared. What that works out to:

20%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Karnataka registration department

In Karnataka it’s called the guidance value.

No government guidance rate is shown for this project.

Karnataka's guidance-value gazettes are in Horizon's record, but this project's address doesn't name a place any of its sub-registrar's tables print.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RERA Karnataka · Approved building plan

BBMP - Bruhat Bengaluru Mahanagara Palike

Municipal / Corporation
Building Permit

The promised possession date (31 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

BBMP

Municipal Corporation · Bruhat Bengaluru Mahanagara Palike

Has approved 2,111 RERA projectsabout 1 in 4 in Karnataka, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
1,619
On record
1,14,417 flats · 373 plots
Reach
9 taluks
Since
2017

More apartment-heavy than Karnataka overall — 100% apartments here vs 62% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Karnataka

07

Other projects nearby

The register · within 25 km

1,038 residential projects still under way within 25 km. Step out ring by ring:

Of the 579 projects the radar draws within 6 km — every kind, every stage — 127 are residential projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

770 m awayApartment

SREE ADITHYA PRIDE

SREE ADITHYA DEVELOPERS · Bengaluru East

May 2024started
Jun 2027target completion
Declared cost₹43.50 CrScale120 flatsAuthorityRERA Karnataka
850 m awayApartment

Aryav Windfields

Aryav Constructions · Bengaluru East

Aug 2024started
Dec 2027target completion
Declared cost₹46.58 CrScale97 flatsAuthorityRERA Karnataka

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.