01

Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
10 × 2BHK, 10 × 3BHK
Saleable area
109–135 sq mper unit, as filed
Floors
5
Land area
745 sq m
Built-up area
1,846 sq m

Timeline

RERA approvedMay 2026
Proposed completionMay 2029
TodaySep 2026
Construction progress

0% overall, as filed

Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
NAVY SRI ANANTH RESIDENCY12BHK1101 of 1
NAVY SRI ANANTH RESIDENCY12BHK1091 of 1
NAVY SRI ANANTH RESIDENCY13BHK1351 of 1
NAVY SRI ANANTH RESIDENCY13BHK1321 of 1
NAVY SRI ANANTH RESIDENCY22BHK1101 of 1
NAVY SRI ANANTH RESIDENCY22BHK1091 of 1
NAVY SRI ANANTH RESIDENCY23BHK1351 of 1
NAVY SRI ANANTH RESIDENCY23BHK1321 of 1
NAVY SRI ANANTH RESIDENCY32BHK1101 of 1
NAVY SRI ANANTH RESIDENCY32BHK1091 of 1
NAVY SRI ANANTH RESIDENCY33BHK1351 of 1
NAVY SRI ANANTH RESIDENCY33BHK1321 of 1
NAVY SRI ANANTH RESIDENCY42BHK1101 of 1
NAVY SRI ANANTH RESIDENCY42BHK1091 of 1
NAVY SRI ANANTH RESIDENCY43BHK1351 of 1
NAVY SRI ANANTH RESIDENCY43BHK1321 of 1
NAVY SRI ANANTH RESIDENCY52BHK1101 of 1
NAVY SRI ANANTH RESIDENCY52BHKmortgaged1091 of 1
NAVY SRI ANANTH RESIDENCY53BHKmortgaged1351 of 1
NAVY SRI ANANTH RESIDENCY53BHKmortgaged1321 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the builder that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Builder registration

S S CONSTRUCTIONS

ProprietorshipPromoter type
Ranga Reddy, TelanganaBased in
46Projects
12Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
758 homes · 132 plotson the public record across 46 projects
86,742 sq mbuilt-up filed
33,295 sq mland declared
₹60.43 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation26 of 43 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority9 of 43 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project4 of 43 projects
BhopalTown & Country Planning (DTCP)3 of 43 projects
Commissioner, APCRDAMunicipal / Corporation1 of 43 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from S S CONSTRUCTIONS— the full portfolio →

03

Location

RERA Telangana · Registration filing
Locality
HMDA Layout, Uppal Bhagath
Village
Uppal Bhagayath
Mandal
Uppal
District
Medchal-Malkajgiri
Pincode
500039
North boundary
Plot No 965
East boundary
Plot No 962 And 963
South boundary
Part Of Plot No 961 And 60 Feet Wide ROAD
West boundary
Plot No 960
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 827m away · Clinic within 2km
LifestylePark 878m away
ShoppingSupermarket 1.6km away · Mall 509m away · Bank 966m away
Getting around
Expressway 249 m · Inner Ring RoadPrimary road 1.9 km · Inner Ring RoadRailway line 2.1 km · chaitanyapuri metroMetro station 534m away (Nagole)Limited bus connectivity nearby
Water & environment
River 293 m · Musi River
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Government Guidance Rate

Telangana Registration & Stamps

In Telangana it’s called the market value — the registration department's figure, not a sale price.

₹24,900per sq yd
₹29,780per sq m
₹3,000per sq ft for a flat · same schedule
Which rate
residential (urban)
Matched to
The rate published for the village of “UPPAL BAGATH (M)”.
In force
effective May 2026

Elsewhere in the same village

MUSI RIVER BUFFER ZONE₹16,983 / sq m₹14,200 / sq yd
RESIDENTIAL LOCALITIES OF UPPAL BAGATH VILLAG₹29,780 / sq m₹24,900 / sq yd
KURMA NAGAR₹29,780 / sq m₹24,900 / sq yd
UPPAL HILLS₹29,780 / sq m₹24,900 / sq yd
NEW RESIDENTIAL LOCALITIES₹29,780 / sq m₹24,900 / sq yd
UPPAL X ROAD TO MUSI RIVER₹55,972 / sq m₹46,800 / sq yd

The same schedule, published for the places around this one — so the figure above reads in its neighbourhood, not alone.

What this number is — and isn’t

  • The minimum value Telangana’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit no. 0152/MMC/SWBP/UPL2/2026Survey no. 1 To 40, 505P, 510 To 564, 282 To 368, 369P, 370 To 373, 374P, 375 To 387, 395 To 401, 454, 456 To 459
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan 0152/MMC/SWBP/UPL2/2026 on the approving authority’s portal to confirm the approval.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Telangana

07

Other projects nearby

The register · within 25 km

2,022 residential projects still under way within 25 km. Step out ring by ring:

Of the 696 projects the radar draws within 6 km — every kind, every stage — 312 are residential projects still under way. This list keeps only those, and looks further out.

7 projects within 1 km — showing the nearest 6.

UPPAL BHAGATResidential

RAJ RESIDENCY

SAMEEKSHA BUILDERS AND DEVELOPERS

Aug 2023registered
Aug 2026target completion
Government Guidance Rate₹24,900/sq ydScale15 flatsAuthorityRERA Telangana
HMDA layoutResidential

HARMONY HEIGHTS

ALTERRA PROJECTS PRIVATE LIMITED

Jun 2024registered
May 2027target completion
Government Guidance Rate₹25,200/sq ydScale10 flatsAuthorityRERA Telangana
NAGOLEResidential

SAIRAM CONSTRUCTIONS

M/S. SAIRAM CONSTRUCTIONS

Jun 2021registered
Jun 2027target completion
Government Guidance Rate₹25,200/sq ydScale10 flatsAuthorityRERA Telangana
fathullaguda villageResidential

VARAMALA

AISHWARYA BUILDERS & DEVELOPERS

Sep 2023registered
Sep 2026target completion
Government Guidance Rate₹15,800/sq ydScale15 flatsAuthorityRERA Telangana
UPPAL BHAGAYATResidential

JUBILEE ROYAL GARDEN

M/S. JUBILEE INFRATECH PVT LTD

Sep 2024registered
Sep 2027target completion
Government Guidance Rate₹25,200/sq ydAuthorityRERA Telangana
UPPALResidential

SREE LAKSHMI RESIDENCY

MAHANKALI ARAVIND

Jul 2025registered
Jul 2028target completion
Government Guidance Rate₹25,200/sq ydScale20 flatsAuthorityRERA Telangana

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.