HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
326 units
Unit mix
245 × 3BHK, 81 × 2BHK
Saleable area
69–124 sq mper unit, as filed
Floors
6
Buildings
3
Land area
16,213 sq m
Built-up area
32,836 sq m
Road widening
99 sq mland set aside for road widening

Timeline

RERA approvedMar 2019
Proposed completionJan 2029
TodayJul 2026
Construction progress

73.2% overall, as filed

Podiums0%
Flat fit-out46%
External finishes59%
OC-readiness65%
Stairs & lifts84%
Superstructure89%
Internal finishes89%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

114 of 326 available
BuildingFloorTypeArea sq mAvailable
BLOCK C12BHK900 of 6
BLOCK C12BHK690 of 3
BLOCK C22BHK900 of 6
BLOCK C22BHK690 of 5
BLOCK C32BHK690 of 5
BLOCK C32BHK900 of 6
BLOCK C42BHK900 of 6
BLOCK C42BHK690 of 5
BLOCK C52BHK690 of 5
BLOCK C52BHK900 of 6
BLOCK C62BHK690 of 5
BLOCK C62BHK900 of 6
BLOCK D13BHK1240 of 6
BLOCK D13BHK1110 of 8
BLOCK D23BHK1240 of 6
BLOCK D23BHK1110 of 8
BLOCK D33BHK1240 of 6
BLOCK D33BHK1110 of 8
BLOCK D43BHK1240 of 6
BLOCK D43BHK1110 of 8
BLOCK D53BHK1240 of 6
BLOCK D53BHK1110 of 8
BLOCK D63BHK1240 of 6
BLOCK D63BHK1110 of 8
BLOCK E13BHK1176 of 6
BLOCK E12BHK871 of 2
BLOCK E13BHK1232 of 8
BLOCK E13BHK10610 of 12
BLOCK E22BHKmortgaged871 of 1
BLOCK E23BHKmortgaged1173 of 3
BLOCK E23BHK1173 of 3
BLOCK E22BHK870 of 2
BLOCK E23BHK1230 of 8
BLOCK E23BHKmortgaged1068 of 8
BLOCK E23BHK1063 of 5
BLOCK E33BHK1176 of 6
BLOCK E32BHK871 of 3
BLOCK E33BHK10611 of 13
BLOCK E33BHK1232 of 8
BLOCK E42BHK871 of 3
BLOCK E43BHK1232 of 8
BLOCK E43BHK1175 of 6
BLOCK E43BHK10610 of 13
BLOCK E53BHK1176 of 6
BLOCK E52BHK871 of 3
BLOCK E53BHK10611 of 13
BLOCK E53BHK1232 of 8
BLOCK E63BHK1176 of 6
BLOCK E63BHK10612 of 13
BLOCK E62BHK870 of 3
BLOCK E63BHK1231 of 8

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

MODI BUILDERS & INFRASTRUCTURES PRIVATE LIMITED

CompanyPromoter type
Hyderabad, TelanganaBased in
7Projects
5Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,566 homes · 413 plotson the public record across 7 projects
3,02,016 sq mbuilt-up filed
1,63,460 sq mplotted area
2,53,053 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority6 of 7 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
HAYATHNAGAR
Mandal
Hayathnagar
District
Ranga Reddy
Pincode
501505
North boundary
ROAD
East boundary
LAND BELONGING TO VENDEE
South boundary
NEIGHBOURS LAND
West boundary
ROAD
What’s nearby
Schools3 schools within 1km · 3 educational institutions within 1km
HealthcareHospital 217m away · Clinic within 2km
LifestylePark 1.2km away · 3 restaurants and cafes within 1km
ShoppingSupermarket 442m away · Bank 83m away
Getting around
Expressway 14 m · Vijaywada HighwayPrimary road 3.9 km · Hyderabad - Nagarjuna Sagar RoadNo metro or railway within 5km2 bus stops within 500m
Water & environment
Water body 932 m · Batula Cheruvu
distances only — not a flood assessment
Declared external development
Community Building…100%
Sewage100%
Solid waste100%
Renewable energy100%
Fire safety100%
Electricity100%
Water supply100%
Sewerage (Chamber,…100%
Rainwater90%
Green Strip/TOT LO…90%
Street lighting90%
Roads90%
Rainwater80%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C3/05335/2019Survey no. 183(P), 203(P)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C3/05335/2019 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.