HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
8 spaces
Land area
686 sq m
Sanctioned built-up
940 sq m

Timeline

RERA registeredJul 2020
Proposed completionMar 2022
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Deepak Developers

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2020–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Wadgaon Bk
Taluka
Haveli
District
Pune
Pincode
411041
Survey no.
51/4C/1B
North boundary
Kirti Nagar
East boundary
Sneh Apartments
South boundary
S No 50
West boundary
Mr Jadhav Property
What’s nearby
SchoolsNearest school 1.6km away · Library 914m away
HealthcareHospital 64m away · Clinic within 2km · Pharmacy within 1km
Lifestyle1 park within 500m · Gym or sports centre 126m away · 9 restaurants and cafes within 1km
ShoppingSupermarket 129m away · Convenience store within 1km · Bank 478m away
Getting around
Expressway 230 mPrimary road 81 m · Narveer Tanaji Malusare MargMetro station 4.5km away (Kothrud)9 bus stops within 500m
Water & environment
Canal 251 m · Mutha Right Bank CanalRiver 1.2 km · Mutha
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 51/4C/1B

The promised possession date (1 Mar 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.