Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
44 spaces
Land area
557 sq m
Sanctioned built-up
956 sq m

Timeline

RERA registeredOct 2023
Proposed completionMar 2025
TodayJul 2026
Construction progress
Podiums0%
Storm Water Drains0%
Solid Waste Manage…50%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Sewerage (Chamber,…100%
Energy managemcnt100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Deep Developers

PartnershipPromoter type
Pune, MAHARASHTRABased in
9Projects
7Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
873 homes · 297 plotson the public record across 9 projects
48,699 sq mbuilt-up filed
8,146 sq mland declared
₹46.93 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation2 of 9 projects
Rajkot Municipal CorporationMunicipal / Corporation2 of 9 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 9 projects
BurhanpurTown & Country Planning (DTCP)1 of 9 projects
Gandhinagar Urban Development AuthorityUrban Development Authority1 of 9 projects
KhandwaTown & Country Planning (DTCP)1 of 9 projects
Pmc Punethis project1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Dhayari (Part)
Taluka
Haveli
District
Pune
Pincode
411041
Survey no.
Survey No 129 Hissa 10/3
North boundary
Survey No 129 Hissa No 10 Part
East boundary
6 Mtrs Wide Road
South boundary
D P 30 Mtrs Wide Road
West boundary
Survey No 129 Hissa No 10 Part
What’s nearby
SchoolsNearest school 1.8km away · College or university 1.4km away · Library 1.8km away
HealthcareHospital 752m away · Clinic within 2km · Pharmacy within 500m
LifestylePark 1.2km away · Gym or sports centre 913m away · 8 restaurants and cafes within 1km
ShoppingSupermarket 775m away · Mall 1.6km away · Convenience store within 1km
Getting around
Expressway 1.1 km · Katraj - Dehu Road BypassPrimary road 402 m · Narveer Tanaji Malusare MargNo metro or railway within 5km8 bus stops within 500m
Water & environment
Canal 324 m · Mutha Right Bank CanalRiver 1.8 km · Mutha
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pmc Pune

Building Permit
Survey no. Survey No 129 Hissa 10/3

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.