8,845 homeson the public record across 18 projects
7,34,185 sq mbuilt-up filed
41,178 sq mland declared
These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Old Survey no. 44/15 (pt), 44/19 (pt), New Survey no. 4/B/20(pt)
North boundary
Runwal Gardens Phase 1 and Internal Driveway
East boundary
24 m wide DP Road
South boundary
PG 21
West boundary
Building No 44 and RG 23
What’s nearby
Schools1 school within 500m · 3 educational institutions within 1km
HealthcareHospital 318m away · Clinic within 2km
LifestylePark 930m away
ShoppingNo supermarket within 2km · Bank 423m away
Getting around
Expressway 4.5 km · Kalyan Bhiwandi RoadPrimary road 12 m · Kalyan - Shil RoadRailway line 2.4 km · Mumbai-Pune RailwayRailway station 2.5km away (Thakurli)Limited bus connectivity nearby
Water & environment
Water body 201 m · Ganapati Visarjan PondRiver 1.1 km
distances only — not a flood assessment
Location — done
04
Government Guidance Rate
Maharashtra IGR — Annual Statement of Rates
In Maharashtra it’s called the ready reckoner rate.
₹49,415per sq yd
₹59,100per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 1 divisions of “gharivle” — the city's middle, not this project's own division.
In force
2026-2027 schedule
What this number is — and isn’t
The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
MahaRERA · Approved building plan
Mumbai Metropolitan Region Development Authority
Metropolitan Development Authority
Building Permit
Survey no. Old Survey no. 44/15 (pt), 44/19 (pt), New Survey no. 4/B/20(pt)
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
Mumbai Metropolitan Region Development Authority
Metropolitan / development authority
Has approved 152 RERA projects — 0.8% of Maharashtra.
an apartments market — 99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.
Builders
93
On record
7,406 flats · 157 plots
Reach
5 districts
Since
2017
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
A disposed complaint may have been resolved for or against the builder, and only disputes escalated to MahaRERA appear here at all.
Number
Date
Status
CC12600477
27 Jan 2026
Roznama Approvedopen
CC12504509
17 Dec 2025
Order Approveddisposed
What the builder declared
Declared to MahaRERA
Litigation
None declared to MahaRERA
Encumbrance
Declared financial encumbrance on the projectworth checking
The builder's own declaration at registration — not a court's or MahaRERA's finding. A flagged line is worth checking with MahaRERA.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with MahaRERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
3,187 residential projects still under way within 25 km. Step out ring by ring:
Of the 1,491 projects the radar draws within 6 km — every kind, every stage — 596 are residential projects still under way. This list keeps only those, and looks further out.
26 projects within 1 km — showing the nearest 6.
gharivleResidential / Group Housing
Runwal Gardens Phase 4 Bldg No. 37
Runwal Residency Private Limited
4 yr 1 mo
Feb 2022registered
Mar 2026target completion
⚠ 4 open complaintsGovernment Guidance Rate₹49,415/sq ydScale282 flatsAuthorityMahaRERA