Rushabh Platinum

P52400078754 · MahaRERA · https://gethorizon.in/projects/rushabh-platinum-latur-m-cl-eo74vmhx

01

Complete project overview

MahaRERA · Registration filing
Units
70 units
Floors
5
Buildings
4
Parking
107 spaces
Land area
2,341 sq m
Sanctioned built-up
6,977 sq m

Timeline

RERA registeredJan 2025
Proposed completionMar 2027
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Landscaping & Tree…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Open Parking0%
Storm Water Drains25%
Electrical meter r…25%
OC-readiness35%
Internal Roads & F…40%
Water Supply50%
Flat fit-out75%
External finishes75%
Sewerage (Chamber,…75%
Internal finishes85%
Stairs & lifts90%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure1000%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

RUSHABH INFRA

PartnershipPromoter type
Latur, MAHARASHTRABased in
2Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
150 homeson the public record across 2 projects
6,977 sq mbuilt-up filed
4,708 sq mland declared
₹16.00 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Latur Municipal CorporationMunicipal Corporationthis project1 of 2 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from RUSHABH INFRA— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Latur (M Cl)
Taluka
Latur
District
Latur
Pincode
413512
Survey no.
SURVEY No. 159/2 , Final Plot No 4
North boundary
Land belongs to Aradhya
East boundary
Plot No 3
South boundary
12 Meter wide Road
West boundary
Plot No 5
What’s nearby
SchoolsNearest school 1.7km away · 4 educational institutions within 1km · College or university 441m away
HealthcareHospital 529m away · 1 clinic within 1km
LifestylePark 682m away · Swimming pool within 2km
ShoppingSupermarket 405m away · Mall 1.8km away
Getting around
Expressway 436 mPrimary road 1.8 km · Main Road LaturRailway line 4.7 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 2.3 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹25,820per sq yd
₹30,880per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Latur (M Cl)”.
In force
2026-2027 schedule
Spread
₹18,763₹52,425 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Latur Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY No. 159/2 , Final Plot No 4
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Latur Municipal Corporation

Municipal corporation

Has approved 32 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
29
On record
204 flats · 0 plots
Since
2019

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

45 residential projects still under way within 25 km. Step out ring by ring:

Of the 98 projects the radar draws within 6 km — every kind, every stage — 37 are residential projects still under way. This list keeps only those, and looks further out.

4 projects within 1 km — showing the nearest 4.

LaturResidential / Group Housing

RAMKRUSHNAHARI PARK PHASE 2 Residential

SURAJ MAHADEV JATAL

Oct 2024registered
Mar 2027target completion
Government Guidance Rate₹25,820/sq ydAuthorityMahaRERA
LaturResidential / Group Housing

Govind Dham Ph 1

NAMAMI DEVI NARMADE INFRASTRUCTURE

Jul 2026registered
Dec 2026target completion
Government Guidance Rate₹25,820/sq ydScale6 flatsAuthorityMahaRERA
LaturResidential / Group Housing

Happy Planet

M/S Barure B.K. And Developers

Aug 2026registered
Dec 2030target completion
Government Guidance Rate₹25,820/sq ydScale56 flatsAuthorityMahaRERA
LaturResidential / Group Housing

HAPPY HERITAGE

BARURE B K AND DEVELOPERS

Oct 2025registered
Dec 2029target completion
Government Guidance Rate₹25,820/sq ydScale35 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.