HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
4
Buildings
2
Parking
38 spaces
Land area
1,079 sq m
Sanctioned built-up
1,899 sq m

Timeline

RERA registeredAug 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Flat fit-out50%
Internal finishes75%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Vijaykumar Pirulal Agarwal

IndividualPromoter type
Pune, MAHARASHTRABased in
1Projects
1Cities
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
District
Pune
Pincode
411014
Survey no.
SR NO 32/4
North boundary
GULMOHAR SYMPHONY PHASE 2
East boundary
SR NO 10
South boundary
15 FT ROAD
West boundary
TUKARAM NAGAR ROAD
What’s nearby
SchoolsNearest school 1.3km away · Library 723m away
HealthcareHospital 416m away · 3 clinics within 1km · Pharmacy within 1km
LifestylePark 986m away · Gym or sports centre 1.3km away · 15+ restaurants and cafes within 1km
ShoppingSupermarket 470m away · Mall 423m away · Convenience store within 500m
Getting around
Expressway 368 m · Kharadi BypassPrimary road 1.9 km · Mundhwa RoadRailway line 2.6 km · Pune - Daund Railway LineRailway station 2.2km away (Ramwadi Station)Limited bus connectivity nearbyAirport 4.2km away
Water & environment
Water body 1.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Others

Building Permit
Survey no. SR NO 32/4
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Others

Planning authority

Has approved 30 RERA projects0.1% of Maharashtra.

an apartments market97% apartments · 3% plotted layouts. Apartments like yours are this body's core business.

Builders
27
On record
813 flats · 264 plots
Reach
11 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.