HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
18
Buildings
10
Parking
471 spaces
Land area
9,449 sq m
Sanctioned built-up
35,979 sq m
Recreational open space
7,734 sq m

Timeline

RERA registeredOct 2019
Proposed completionDec 2026
TodayJul 2026
Construction progress
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Community Building…100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Aggregate area of …100%
Internal finishes1001%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Gera Developments Private Limited

CompanyPromoter type
Pune, MAHARASHTRABased in
25Projects
3Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,150 homeson the public record across 25 projects
6,05,694 sq mbuilt-up filed
1,53,061 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Metropolitan Region Development AuthorityMetropolitan Development Authoritythis project11 of 13 projects
Pune Municipal CorporationMunicipal Corporation2 of 13 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
WAGHOLI
Taluka
Haveli
District
Pune
Pincode
412207
Survey no.
Gat no 1343B Part
North boundary
By Part OS of Geras WOJ and part project L and D
East boundary
By Part open space of Geras WOJ and Part Project L
South boundary
By proposed 24mtr wide road and GAT NO 1284 beyond
West boundary
By Part Geras WOJ D and proposed 24mtr wide road
What’s nearby
SchoolsNearest school 1.4km away · Library 661m away
HealthcareHospital 167m away · 2 clinics within 1km · Pharmacy within 500m
LifestylePark 1.7km away · Gym or sports centre 1.8km away · 18+ restaurants and cafes within 1km
ShoppingSupermarket 467m away · Mall 1.0km away · Convenience store within 500m
Getting around
Expressway 633 m · Kharadi BypassPrimary road 2.7 km · Mundhwa RoadRailway line 3.4 kmRailway station 1.8km away (Ramwadi Station)Limited bus connectivity nearbyAirport 3.3km away
Water & environment
Water body 1.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. Gat no 1343B Part
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Apartments like yours are this body's core business.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation3 cases on record, earliest 2018
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.